E3 Lithium Begins Operations of Alberta’s First Direct Lithium Extraction Field Pilot Plant

CALGARY, Alberta--(BUSINESS WIRE)--E3 LITHIUM LTD. (TSXV: ETL) (FSE: OW3) (OTCQX: EEMMF), “E3 Lithium” or the “Company,” Alberta’s leading lithium developer and extraction technology innovator, announces that commissioning of its Direct Lithium Extraction (DLE) field pilot plant is complete and operations have begun.

The commissioning process included connecting all major pieces of equipment to the piping and wiring systems on site. The team has also conducted a series of necessary inspections and system tests to ensure safe and successful operations. Each DLE system has demonstrated it is operating as expected based on the performance metrics established during pre-pilot testing.

The operations begin with running the DLE processes at different system parameter settings to determine the most efficient extraction of lithium, guided by the Key Performance Indicators (KPIs) outlined on June 14, 2023. Upon determining a specific set of operating parameters, each system will run for a longer duration to accomplish two tasks: 1) confirm consistent results over an extended period; and 2) produce large volumes of lithium concentrate for further refining into lithium products, such as lithium hydroxide. The data collected throughout the pilot operations will be primarily used to inform the commercial design of the processing facility for our Pre-Feasibility Study (PFS) and Feasibility Study (FS).

“The start of full operations is a testament to the hard work the team has been putting in to get this equipment running,” said Chris Doornbos, President and CEO of E3 Lithium. “This is a foundational moment for E3 Lithium, as demonstrating DLE at pilot scale will enable us to move forward in developing this lithium asset in Alberta towards commercialization.”

E3 Lithium will provide updates as operations progress and will share results, measured against its previously outlined Key Performance Indicators, as they become available.

Please visit www.e3lithium.ca/Lithium1 for the latest photos, videos and pilot-related news.

About E3 Lithium

E3 Lithium is a development company with a total of 16.0 million tonnes of lithium carbonate equivalent (LCE) Measured and Indicated and 0.9 million tonnes LCE Inferred mineral resources1 in Alberta. As outlined in E3’s Preliminary Economic Assessment, the Clearwater Lithium Project has an NPV8% of USD 1.1 Billion with a 32% IRR pre-tax and USD 820 Million with a 27% IRR after-tax1. E3 Lithium’s goal is to produce high purity, battery grade lithium products to power the growing electrical revolution. With a significant lithium resource and innovative technology solutions, E3 Lithium has the potential to deliver lithium to market from one of the best jurisdictions in the world.

ON BEHALF OF THE BOARD OF DIRECTORS

Chris Doornbos, President & CEO
E3 Lithium Ltd.

1: The Preliminary Economic Assessment (PEA) for the Clearwater Lithium Project NI 43-101 technical report is amended Sept 17, 2021. The mineral resource NI 43-101 Technical Report for the North Rocky Property, effective October 27, 2017, identified 0.9Mt LCE (inferred). The mineral resource NI 43-101 Technical Report for the Bashaw District Project, effective March 21, 2023, identified 16.0Mt LCE (measured & indicated). All reports are available on the E3 Lithium’s website (e3lithium.ca/technical-reports) and SEDAR (www.sedarplus.ca).

Forward-Looking and Cautionary Statements

This news release includes certain forward-looking statements as well as management’s objectives, strategies, beliefs and intentions. Forward looking statements are frequently identified by such words as “may”, “will”, “plan”, “expect”, “anticipate”, “estimate”, “intend” and similar words referring to future events and results. Forward-looking statements are based on the current opinions and expectations of management. All forward-looking information is inherently uncertain and subject to a variety of assumptions, risks and uncertainties, including the speculative nature of mineral exploration and development, fluctuating commodity prices, the effectiveness and feasibility of emerging lithium extraction technologies which have not yet been tested or proven on a commercial scale or on the Company’s brine, competitive risks and the availability of financing, as described in more detail in our recent securities filings available at www.sedarplus.ca. Actual events or results may differ materially from those projected in the forward-looking statements and we caution against placing undue reliance thereon. We assume no obligation to revise or update these forward-looking statements except as required by applicable law.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts

E3 Lithium - Investor and Media Relations
Greg Foofat
Manager, Investor Relations
investor@e3lithium.ca
587-324-2775

E3 Lithium Ltd.

TSX VENTURE:ETL

Release Versions
$Cashtags

Contacts

E3 Lithium - Investor and Media Relations
Greg Foofat
Manager, Investor Relations
investor@e3lithium.ca
587-324-2775

Social Media Profiles
More News From E3 Lithium Ltd.

E3 Lithium Joins Consortium to Develop LMR Cathode Anchored by POSCO and the National Research Council of Canada

CALGARY, Alberta--(BUSINESS WIRE)--E3 LITHIUM LTD. (TSXV: ETL) (FSE: OW3) (OTCQX: EEMMF), “E3”, “E3 Lithium” or the “Company,” a leader in Canadian lithium development has entered into a collaborative research agreement (the “Project”) between E3, the National Research Council of Canada (“NRC”), and major South Korean battery manufacturer POSCO through its subsidiary POSCO AMERICA CORPORATION (“POSCO”), among other input contributors, whereby E3 will be the exclusive lithium carbonate provider...

E3 Lithium Approaches Completion of Phase 2 of its Demonstration Facility and Outlines Path to Commercialization

CALGARY, Alberta--(BUSINESS WIRE)--E3 LITHIUM LTD. (TSXV: ETL) (FSE: OW3) (OTCQX: EEMMF), “E3”, “E3 Lithium”, or the “Company” is approaching completion of Phase 2 of its Demonstration Facility and provides an update on the progress of its Clearwater Project toward commercial production. Phase 2 of the Demonstration Facility provides the last major piece of data required to complete the design of the commercial facility. The completion of Phase 2 will mark an important engineering milestone and...

E3 Lithium Confirms Listing of Warrants in Relation to Recently Closed Equity Offering

CALGARY, Alberta--(BUSINESS WIRE)--E3 LITHIUM LTD. (TSXV: ETL) (FSE: OW3) (OTCQX: EEMMF) (“E3”, “E3 Lithium” or the “Company”), a leader in Canadian lithium development, is pleased to announce, further to its announcement on September 24, 2026, that an aggregate of 12,782,250 common share purchase warrants (“Warrants”) are expected to commence trading on the TSX Venture Exchange on October 2, 2026 under the symbol ETL.WT.A. The Warrants were issued pursuant to the Company’s public offering of u...
Back to Newsroom