BC Works (Kitimat) smelter reduces production following strike

MONTREAL--(BUSINESS WIRE)--Rio Tinto has begun reducing production at its BC Works aluminium smelter in Kitimat, Canada due to a strike initiated by the Unifor Local 2301 union after negotiations failed to reach a new collective labour agreement.

Production will be reduced to around 35 per cent of the smelter’s 432,000 tonne annual capacity, so that it can safely be operated by staff and employees required under an essential services order granted by the BC Labour Relations Board.

Rio Tinto Aluminium managing director Atlantic Operations Samir Cairae said: “Reducing production will have a significant impact on the business and community, but we are committed to taking the necessary steps to operate safely with a reduced workforce.

“We have made every effort to reach a mutually beneficial agreement through negotiating in good faith over the past seven weeks, including proposing an independent mediator which was rejected by Unifor Local 2301.

“We will continue to look for longer term solutions with the union and work closely with customers and suppliers to minimise disruptions.”

A reduced workforce is also in place to ensure the Kemano hydro-power facility continues to run safely.

Rio Tinto employs approximately 1,050 people at the BC Works smelter and Kemano powerhouse, including around 900 employees represented by Unifor Local 2301. The company contributed C$780 million to the economy of British Columbia in 2020.

Contacts

Please direct all enquiries to media.enquiries@riotinto.com

Media Relations, UK

Illtud Harri
M +44 7920 503 600

David Outhwaite
M +44 7787 597 493

Media Relations, Americas
Matthew Klar
T +1 514 608 4429

Media Relations, Australia
Jonathan Rose
M +61 447 028 913

Matt Chambers
M +61 433 525 739

Jesse Riseborough
M +61 436 653 412

Investor Relations, UK
Menno Sanderse
M: +44 7825 195 178

David Ovington
M +44 7920 010 978

Clare Peever
M +44 7788 967 877

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom

T +44 20 7781 2000
Registered in England
No. 719885

Investor Relations, Australia
Natalie Worley
M +61 409 210 462

Amar Jambaa
M +61 472 865 948

Rio Tinto Limited
Level 7, 360 Collins Street
Melbourne 3000
Australia

T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

riotinto.com

Category: BC Works

Rio Tinto

LSE:RIO

Release Summary
BC Works (Kitimat) smelter reduces production following strike
Release Versions

Contacts

Please direct all enquiries to media.enquiries@riotinto.com

Media Relations, UK

Illtud Harri
M +44 7920 503 600

David Outhwaite
M +44 7787 597 493

Media Relations, Americas
Matthew Klar
T +1 514 608 4429

Media Relations, Australia
Jonathan Rose
M +61 447 028 913

Matt Chambers
M +61 433 525 739

Jesse Riseborough
M +61 436 653 412

Investor Relations, UK
Menno Sanderse
M: +44 7825 195 178

David Ovington
M +44 7920 010 978

Clare Peever
M +44 7788 967 877

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom

T +44 20 7781 2000
Registered in England
No. 719885

Investor Relations, Australia
Natalie Worley
M +61 409 210 462

Amar Jambaa
M +61 472 865 948

Rio Tinto Limited
Level 7, 360 Collins Street
Melbourne 3000
Australia

T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

riotinto.com

Category: BC Works

More News From Rio Tinto

BHP and Rio Tinto welcome first Caterpillar battery-electric haul trucks to the Pilbara

PERTH, Australia--(BUSINESS WIRE)--Australia’s first Cat® 793 XE Early Learner battery-electric haul trucks have arrived at BHP’s Jimblebar iron ore mine in the Pilbara, marking the start of on-site testing, in collaboration with Rio Tinto, of Caterpillar’s battery-electric heavy haulage technology in the region that powers the nation’s economy. The two Early Learner trucks, delivered through an industry-first collaboration between BHP, Rio Tinto and Caterpillar represent a major step toward a...

Rio Tinto’s Nuton technology produces first copper

TUCSON, Arizona--(BUSINESS WIRE)--Rio Tinto has successfully produced the first copper from the Johnson Camp mine in Arizona using its Nuton® Technology, marking a pivotal step forward in the development of this innovative copper processing technology. After more than 30 years of research and development, the first copper cathode using Rio Tinto’s proprietary bioleaching technology, which relies on microorganisms grown on site, was produced at Gunnison Copper’s Johnson Camp mine last month. The...

Stronger, sharper and simpler Rio Tinto to deliver leading returns

LONDON--(BUSINESS WIRE)--Rio Tinto will today outline its strategy to deliver industry leading returns by becoming stronger, sharper and simpler, at its 2025 Capital Markets Day. Chief Executive Simon Trott and members of the executive team will detail how Rio Tinto will unlock its full potential to become the most valued metals and mining business through a strategy that starts with having the right assets in the right markets, supported by a diversified model that delivers market-leading perf...
Back to Newsroom