Cadeler Installs Final Turbine at He Dreiht Offshore Wind Farm

COPENHAGEN, Denmark--(BUSINESS WIRE)--Cadeler has completed the final turbine installation at the 960 MW He Dreiht Offshore Wind Farm in the German North Sea. The final turbines were installed by Wind Keeper, under its long-term contract with Vestas.

Cadeler’s scope of the installation campaign was executed using two of Cadeler's offshore wind installation vessels. Wind Orca commenced the project in April 2025 before Wind Keeper took over the remaining installation scope in the first quarter of 2026 under Cadeler's long-term contract with Vestas announced last year. The project marked Wind Keeper's first offshore wind installation campaign since joining the Cadeler fleet following her acquisition and comprehensive upgrade.

Developed by EnBW, He Dreiht consists of 64 Vestas V236-15.0 MW wind turbines and marks the first commercial-scale installation of Vestas' flagship offshore wind turbine. Once fully operational, the wind farm will generate enough renewable electricity to supply approximately 1.1 million households.

Henrik Thun, He Dreiht Project Director at Vestas, comments: "The completion of turbine installation at He Dreiht is an important milestone for our V236-15.0 MW platform and a testament to what can be achieved through strong collaboration across the offshore value chain. We thank Cadeler for supporting the safe and efficient installation of all 64 turbines and look forward to progressing the project through commissioning and into operation."

Commenting on the project completion, Mikkel Gleerup, CEO of Cadeler, says: "We are proud to have supported Vestas in successfully delivering the first commercial installation campaign for the V236-15.0 MW turbine. Projects of this scale are made possible through a shared commitment to safe, predictable execution. The project also marks Wind Keeper's successful debut as part of the Cadeler fleet, strengthening our ability to provide long-term support for our clients across both the construction and operational phases of offshore wind projects."

Equipped with a 2,200-tonne main crane, Wind Keeper supports both offshore wind installation and operations and maintenance activities through Cadeler's dedicated service platform, Nexra.

The He Dreiht Offshore Wind Farm is located approximately 90 kilometres northwest of Borkum and around 110 kilometres west of Helgoland in the German North Sea.

About Cadeler:

Cadeler A/S (Cadeler) is a pure-play offshore wind installation partner and a global leader in offshore wind turbine transport and installation. The company owns and operates the industry’s largest fleet of jack-up offshore wind installation vessels and is expanding its capabilities into full-scope foundation transport and installation, as well as operations & maintenance. With its modern fleet and depth of expertise across onshore and offshore operations, Cadeler supports the safe, efficient and reliable delivery of offshore wind projects worldwide. Cadeler is listed on the New York Stock Exchange (ticker: CDLR) and the Oslo Stock Exchange (ticker: CADLR). For more information, please visit www.cadeler.com.

Contacts

For further information, please contact:

Cadeler Press Office:
press@cadeler.com

Mikkel Gleerup
CEO, Cadeler
+45 3246 3102
mikkel.gleerup@cadeler.com

Alexander Simmonds
EVP & CLO, Cadeler
+44 7376 174172
alexander.simmonds@cadeler.com

Cadeler A/S

NYSE:CDLR

Release Versions

Contacts

For further information, please contact:

Cadeler Press Office:
press@cadeler.com

Mikkel Gleerup
CEO, Cadeler
+45 3246 3102
mikkel.gleerup@cadeler.com

Alexander Simmonds
EVP & CLO, Cadeler
+44 7376 174172
alexander.simmonds@cadeler.com

More News From Cadeler A/S

Cadeler Significantly Expands Its Capabilities in Offshore Wind Foundation T&I With the Acquisition of Menck

COPENHAGEN, Denmark--(BUSINESS WIRE)--Cadeler A/S (or “Cadeler”), a leading offshore wind installation contractor and operator of the industry’s largest fleet of jack-up wind installation vessels, today announces its strategic acquisition of Menck, a leading global provider of specialist equipment and technology solutions for offshore foundation installation. The acquisition strengthens Cadeler’s offshore wind installation capabilities and furthers the company’s ambition to be the preferred ins...

Cadeler Strengthens Future Installation Capacity With Firm Orders for Two New T-class Vessels

COPENHAGEN, Denmark--(BUSINESS WIRE)--Cadeler today announces that it has signed firm contracts with COSCO Shipping Offshore shipyard in Qidong, China, for the construction of two new T-class offshore wind installation vessels, scheduled for delivery in 2030 and 2031. Earlier this year, Cadeler secured the equity financing for this investment as part of its long-term strategy to become the preferred offshore wind installation partner and to support the continued growth of the offshore wind indu...

Cadeler Takes Delivery of 11th Vessel: Wind Ace

COPENHAGEN, Denmark--(BUSINESS WIRE)--Cadeler today announces the successful delivery, within budget and on schedule, of Wind Ace, the company's eleventh wind installation vessel and second of three A-class newbuilds. Cadeler’s A-class vessels are industry leading in flexibility and scope, capable of conversion from the installation of XXL foundations to the installation of wind turbine generators within a short period of time. Wind Ace has been under construction for the past two years at the...
Back to Newsroom