Second Quarter - 30 June 2026 production results

LONDON--(BUSINESS WIRE)-- 

AltynGold Plc

("AltynGold" or the "Company")

Q2 2026 Production and Operational update

London, 10 August 2026 - AltynGold (LSE:ALTN), a leading exploration and development gold miner operating in Kazakhstan, announces its unaudited production and operational update for the three months to 30 June 2026 ("Q2 2026" or the "Period").

The Company delivered a progressive quarter of operations, producing 15.6Koz of gold, up 23.3% from Q1 and remains on track to meet market guidance of 52-55Koz for the full year.

Operational highlights

  • In Q2 2026 the Company operated the Sekisovskoye processing plant at its 1 Mtpa nameplate capacity (full load capacity), following the upgrade completed in December 2024. Ore mined and ore processed rose 15.5% and 12.4% quarter-on-quarter (QoQ) to 246 kt and 264 kt respectively. The QoQ increase reflects the return to normal mining conditions following the planned lower-grade mining of transitional zones in Q1 2026; on a year-on-year (YoY) basis ore mined and ore processed were 1.3% and 6.4% higher.
  • Ore processed was 12.4% higher at 264 kt, at a grade of 1.83 g/t producing 15,610 oz of gold (Q1 2026 12,664 oz). With gold recovery slightly higher at 85.01% the Company increased the gold poured to 13,242 oz (Q1 2026 10,664 oz), a significant increase of 24%.
  • During Q1 2026 the Company carried out planned mining of the upper horizons of ore bodies 5.5 and 6 to 8 to bridge a temporary vertical gap between the main ore bodies. With that work completed, the average mined improved to 1.88 g/t in Q2 2026, up from 1.73 g/t in Q1 2026. Gold poured increased 24.2% QoQ to 13,242 ounces, while on a year-on-year basis gold poured was 4.8% lower, reflecting the lower grade profile.

Financial highlights

Total revenue increased 4.6% QoQ to US$58.9 million (Q1 2026: US$56.3 million). Gold sold rose 13.6% QoQ to 13,096 oz, more than offsetting a 7.3% QoQ decline in the average realised gold price to US$4,459 oz (Q1 2026: US$4,809). On a year-on-year basis, total revenue was 31.8% higher, driven by the higher realised gold price (Q2 2025: US$3,222 per ounce), while gold sold was 4.1% lower.

Gold production and operational figures for the period

 

UoM

Q2 2026

Q1 2026

Change QoQ

Q2 2025

Change YoY

Ore mined

t

245 610

212 595

+15.5%

242 362

+1.3%

Gold grade (mined)

g/t

1.88

1.73

+8.7%

2.01

-6.5%

Contained gold (mined)

oz

14 832

11 792

+25.8%

15 631

-5.1%

Ore processed

t

263 700

234 625

+12.4%

247 946

+6.4%

Gold grade (processed)

g/t

1.84

1.68

+9.5%

2.02

-8.9%

Contained gold (processed)

oz

15 610

12 664

+23.3%

16 069

-2.9%

Gold poured

oz

13 242

10 664

+24.2%

13 906

-4.8%

Gold recovery

%

85.01

84.56

+0.45pp

84.84

+0.17pp

Gold sold

oz

13 096

11 532

+13.6%

13 652

-4.1%

Av. realised price

US$/oz

4 459

4 809

-7.3%

3 222

+38.4%

Total revenue

US$m

58.9

56.3

+4.6%

44.68

+31.8%

Lost-time injuries

Nil

-

-

-

-

-

Management is focusing on completing the studies and licensing work that will define the next phase of growth and look forward to updating the market in the coming few months.

Further Information

For further information, please contact

AltynGold Plc

Rajinder Basra

+44 (0) 203 432 3198

info@altyngold.uk

Hudson Sandler LLP (Public Relations)

Charlie Jack

Kristina Gaysina

+44 (0)207 796 4133

altyngold@hudsonsandler.com

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the UK version of the Market Abuse Regulation (EU) No. 596/2014 which is part of UK law by virtue of the European Union (Withdrawal) Act 2018.

Information on the Company

AltynGold Plc (LSE:ALTN) is an established precious metals producer operating in Kazakhstan, which is listed on the Equity shares (transition) segment of the London Stock Exchange.

To read more about AltynGold please visit our website www.altyngold.uk and follow our news on LinkedIn at AltynGold Plc.

Category Code: MSCL
Sequence Number: 1603077
Time of Receipt (offset from UTC): 20260810T150629+0100

Contacts

AltynGold Plc

AltynGold Plc

LSE:ALTN

Release Versions

Contacts

AltynGold Plc

More News From AltynGold Plc

AltynGold Plc UK Regulatory Announcement: AGM Statement

LONDON--(BUSINESS WIRE)--  AltynGold Plc ("AltynGold" or the "Company") Result of Annual General Meeting London, 3 June 2026 - AltynGold (LSE: ALTN) announces that all the resolutions put forward at its 2026 Annual General Meeting held on 2 June 2026 were passed. Further Information: For further information, please contact: AltynGold Plc Rajinder Basra +44 (0) 203 432 3198 Hudson Sandler LLP (Public Relations) Charlie Jack Kristina Gaysina +44 (0)207 796 4133 altyngold@hudsonsandler.com The inf...

AltynGold Plc UK Regulatory Announcement: AGM Statement

LONDON--(BUSINESS WIRE)--  AltynGold Plc ("AltynGold" or the "Company") Growth Strategy Update and Annual General Meeting London, 1 June 2026 - AltynGold (LSE:ALTN), a leading exploration and development gold miner operating in Kazakhstan, is pleased to provide the following update regarding the ongoing development of its assets. Following a transformational period for the Company, during which it successfully expanded its Sekisovskoye processing capacity to 1 Mtpa on time and on budget, enabli...

AltynGold Plc UK Regulatory Announcement: 1st Quarter Results

LONDON--(BUSINESS WIRE)--  AltynGold Plc ("AltynGold" or the "Company") Q1 2026 Production and Operational update AltynGold (LSE:ALTN), a leading exploration and development gold miner operating in Kazakhstan, is pleased to announce its production and operational update for the three months to 31 March 2026 ("Q1 2026" or the "Period"). Production and revenues Q1 2026 was another strong operational quarter for AltynGold. Ore mined (213kt) and milled (235kt) reflected a 2% and 15% year-over-year...
Back to Newsroom