ComEd Announces New Agreements Signed to Ensure Large Load Customers Pay their Fair Share to Connect with and Use the Grid

New approach protects existing customers from unfair increases in transmission rates, while supporting responsible connection of large load projects

CHICAGO--(BUSINESS WIRE)--ComEd today announced the first set of new Transmission Security Agreements (TSAs) designed to protect customers and ensure fairness in the cost of connecting and providing transmission service to new large loads requesting service from the grid. These agreements help safeguard existing customers from bearing costs of serving proposed large load projects and ensure that those new projects pay their fair share even if they do not fully materialize.

These agreements include revenue commitments tied to the transmission services requested by eight large customers, who represent a forecasted new load greater than 6.5 GW. Together, the eight agreements will prevent existing ComEd customers from bearing responsibility for more than $2 billion in transmission charges over a 10-year period.

Under the TSAs, all existing customers are protected from transmission service costs that should be absorbed by new large load projects, even if those projects do not meet their expected load. Without the TSA, other customers might bear those costs, while under the TSA, the large load applicant will cover the shortfall and the TSA payments the applicant makes will reduce, on a dollar-for-dollar basis, the costs other customers would have to cover. This approach underscores ComEd’s commitment to safeguarding existing customers from unfair financial impact in northern Illinois.

“These new transmission security agreements are a model for how utilities and the developers of large load projects – regardless of industry sector – can come together to meet growing power requests responsibly,” said Gil Quiniones, President and CEO of ComEd. “By having TSAs in place, ComEd can better ensure that the customers who impose very large demands on the system are paying their fair share.”

As part of the TSAs, ComEd will require a firm financial commitment from developers of projects 50MWs or above. This “take or pay” agreement requires collateral for 10 years of transmission service revenues according to the load requirements that ComEd is being asked to serve.

“As the world’s largest data center developer, provider, and operator, we understand the challenge of meeting rapidly growing digital demands while keeping power costs affordable,” said Adrian Anderson, SVP Global Energy for Equinix. “Northern Illinois remains a key market for continued growth, which is why we’re proud to partner with ComEd on this initiative to bring greater transparency to the development process as we continue to drive growth and job creation across all our sites.”

The new TSA provides a replicable approach that will be used for future large load requests, and reduces speculative projects, which will also help ensure that ComEd makes the right levels of investment needed to serve new large loads while upholding system reliability.

Rightsizing ComEd’s pipeline of large load requests and reducing speculative projects are essential steps as future load projections influence energy supply costs in the wholesale power markets. Last year, regional grid operator PJM noted that demand growth, along with constrained supply expansion, is a key contributor to rising supply costs. While ComEd does not own generation, participate in the auction, or profit from the costs associated with PJM auctions, they are passed onto ComEd bills to customers on the supply side of the bill, without any markup.

The new TSAs are just the latest example of how ComEd is acting to protect its existing customers as supply prices continue to rise—from expanding financial assistance options for its hardest hit customers, to advocating for new generation to come online to meet the growing level of demand.

ComEd also proposed a series of retail large load tariff modifications currently before the Illinois Commerce Commission (ICC). The tariff modifications would require higher initial application deposits and larger deposit requirements for the company’s electrical infrastructure installed on a new customer’s property if they do not meet their load request or cover the associated revenue requirement. A decision by the ICC is expected early this year.

ComEd is a unit of Chicago-based Exelon Corporation (NASDAQ: EXC), a Fortune 200 company and one of the nation’s largest utility companies, serving more than 10.7 million electricity and natural gas customers. ComEd powers the lives of more than 4 million customers across northern Illinois, or 70 percent of the state’s population. For more information, visit ComEd.com, and connect with the company on Facebook, Instagram, LinkedIn, X and YouTube.

 

 

Contacts

ComEd
Media Relations
312-394-3500

ComEd

NASDAQ:EXC

Release Versions

Contacts

ComEd
Media Relations
312-394-3500

Social Media Profiles
More News From ComEd

ComEd Marks $350 Million in Distributed Generation Rebates with Streamwood Park District Solar Installation

CHICAGO--(BUSINESS WIRE)--ComEd today highlighted the growing momentum of customer-owned renewable energy across northern Illinois, announcing that its Distributed Generation (DG) program has exceeded $350 million in rebates and incentives while presenting the Streamwood Park District with more than $94,000 to support its solar installation at the Park Place Family Recreation Center. To date, ComEd has 1.8 GW of distributed generation on its grid. Established under the Future Energy Jobs Act an...

ComEd, Solar Landscape and Public Storage Announce 60 New Rooftop Solar Sites Planned for Northern Illinois

CHICAGO--(BUSINESS WIRE)--ComEd yesterday joined Solar Landscape and Public Storage to announce plans to develop 60 rooftop community solar projects —with 10 already livened—across northern Illinois in the next two years, marking one of the largest community solar installations in Illinois. Together, the projects will deliver 44 Megawatts (MW) of community solar energy, boosting grid capacity and creating opportunities for customers to lower their energy costs. ComEd has one of the largest comm...

Students in Illinois Get Ready to Build, Race Electric Vehicles in ComEd’s EV Rally

CHICAGO--(BUSINESS WIRE)--Sixty teens are gearing up for ComEd’s annual EV Rally, a program that immerses students ages 13-18 in electric vehicles (EVs) and introduces science, technology, engineering and math (STEM) principles. The ComEd EV Rally is celebrating the 10th year of this program by expanding participation to host the largest number of participants in the program’s history. These students will learn about the future of energy while connecting with ComEd mentors from across the compa...
Back to Newsroom