PERTH, Australia--(BUSINESS WIRE)--Rio Tinto’s East Intercourse Island (EII) facility at Dampier Port in Western Australia’s Pilbara region has resumed operations after being impacted by Tropical Cyclone Sean.

A railcar dumper at the EII port facility was flooded when Tropical Cyclone Sean delivered record rain along parts of the Pilbara coastline, including 274mm to Karratha, on 20 January 2025.

Dumper operation at EII resumed last week and the first ship was loaded today.

As stated in the full year results on 19 February 2025, operations at the Dampier and Cape Lambert Ports were also impacted by Tropical Cyclone Tahlia, Tropical Cyclone Vince and Tropical Cyclone Zelia, with total losses from all four cyclones anticipated to be about 13 million tonnes in the year to date. Mitigation plans are in place to offset about half of this through the course of the year.

Pilbara iron ore shipment guidance for 2025 remains unchanged at 323 to 338 million tonnes.

As the system rebalances and normal operations resume, an update will be provided in the first quarter operations review on 16 April 2025.

Contacts

Please direct all enquiries to media.enquiries@riotinto.com

Media Relations,
United Kingdom
David Outhwaite
M +44 7787 597 493

Media Relations,
Australia
Matt Chambers
M +61 433 525 739
Michelle Lee
M +61 458 609 322
Rachel Pupazzoni
M +61 438 875 469

Media Relations,
Canada
Simon Letendre
M +1 514 796 4973
Malika Cherry
M +1 418 592 7293
Vanessa Damha
M +1 514 715 2152

Media Relations,
US
Jesse Riseborough
M +1 202 394 9480

Investor Relations,
United Kingdom
Rachel Arellano
M:
+44 7584 609 644
David Ovington
M +44 7920 010 978
Laura Brooks
M +44 7826 942 797
Weiwei Hu
M +44 7825 907 230

Investor Relations,
Australia
Tom Gallop
M +61 439 353 948
Amar Jambaa
M +61 472 865 948

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom
T +44 20 7781 2000
Registered in England
No. 719885

Rio Tinto Limited
Level 43, 120 Collins Street
Melbourne 3000
Australia
T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

riotinto.com

Category: Pilbara

Rio Tinto

LSE:RIO

Release Versions

Contacts

Please direct all enquiries to media.enquiries@riotinto.com

Media Relations,
United Kingdom
David Outhwaite
M +44 7787 597 493

Media Relations,
Australia
Matt Chambers
M +61 433 525 739
Michelle Lee
M +61 458 609 322
Rachel Pupazzoni
M +61 438 875 469

Media Relations,
Canada
Simon Letendre
M +1 514 796 4973
Malika Cherry
M +1 418 592 7293
Vanessa Damha
M +1 514 715 2152

Media Relations,
US
Jesse Riseborough
M +1 202 394 9480

Investor Relations,
United Kingdom
Rachel Arellano
M:
+44 7584 609 644
David Ovington
M +44 7920 010 978
Laura Brooks
M +44 7826 942 797
Weiwei Hu
M +44 7825 907 230

Investor Relations,
Australia
Tom Gallop
M +61 439 353 948
Amar Jambaa
M +61 472 865 948

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom
T +44 20 7781 2000
Registered in England
No. 719885

Rio Tinto Limited
Level 43, 120 Collins Street
Melbourne 3000
Australia
T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

riotinto.com

Category: Pilbara

More News From Rio Tinto

Rio Tinto expands solar power capacity at Kennecott

SALT LAKE CITY--(BUSINESS WIRE)--Rio Tinto has energized a new 25-megawatt solar plant at its Kennecott copper operations in Utah, showcasing a circular critical-minerals supply chain in which tellurium produced at the site is used to manufacture the panels now powering it. Together with the 5MW solar plant completed in 2023, Kennecott now has 30MW of solar capacity—enough to power approximately 1,026 average American homes annually and reduce Kennecott’s Scope 2 emissions by about 6% (20,000 t...

Rio Tinto and Amazon Web Services collaborate to bring low-carbon Nuton copper to U.S. data centres

TUCSON, Ariz.--(BUSINESS WIRE)--Rio Tinto today announces a strategic collaboration with Amazon Web Services (AWS) that will see AWS become Nuton® Technology’s first customer following the breakthrough industrial-scale deployment of the innovative bioleaching technology at the Johnson Camp copper mine in the U.S. last month. Under the two-year agreement, AWS will use the first Nuton copper ever produced in components of its U.S. data centres, while also providing cloud-based data and analytics...

Rio Tinto and BHP explore collaboration to mine up to 200 million tonnes of Pilbara iron ore

PERTH, Australia--(BUSINESS WIRE)--Rio Tinto and BHP have agreed to work together to extract up to 200 million tonnes of iron ore at their neighbouring Yandicoogina and Yandi iron ore operations in the Pilbara. Under two non-binding Memoranda of Understanding (MOUs), the companies will explore the potential for: Collaboration on the development of Rio Tinto’s Wunbye deposit; and BHP to supply its Yandi Lower Channel Deposit ore to Rio Tinto for processing at its existing wet plants under agreed...
Back to Newsroom