Avangrid Produces First Energy from True North Solar Project in Texas, Construction Continues On Schedule

Avangrid has commissioned 20MW of the project thus far, with commercial operations expected to begin by the end of the year

FALLS COUNTY, Texas--(BUSINESS WIRE)--Avangrid, Inc. (NYSE: AGR), a leading sustainable energy company and member of the Iberdrola Group, announced that it has begun to produce power from the True North solar project in Falls County, Texas, near Waco. With 20 MW commissioned thus far, this marks another major milestone for what will become the largest solar power project in Avangrid’s portfolio, and its first solar project in Texas.

“This is great news, not just for the on-time construction of True North, but for the state of Texas at large. Thanks to the diligent work of our team and our contractors, we are able to supply additional energy to the Texas electrical grid as we move into the summer months,” said Pedro Azagra, Avangrid CEO. “I am happy to see this project moving forward as Avangrid continues on its mission to accelerate the clean energy transition across America.”

True North will be a 238 MWac (321 MWdc) solar farm. Once the project is built, it will supply clean, renewable energy in support of Meta’s net zero commitment, including supporting its upcoming data center in neighboring Temple, its second data center facility in Texas, with 100 percent renewable energy. Ahead of commercial operations, expected at the end of 2024, the project will supply power to customers on the Texas grid.

During its construction and operation, the project is creating local jobs and supporting local communities. It is expected to pay more than $40 million in property taxes over the life of the project, which directly supports public services like safety and fire protection, as well as local schools.

Avangrid has successfully developed, built, and operated renewable energy facilities in Texas for more than 15 years, with more than 1,200 MW of installed wind capacity. The company has paid more than $100 million in property taxes from its existing facilities.

About Avangrid: Avangrid, Inc. (NYSE: AGR) aspires to be the leading sustainable energy company in the United States. Headquartered in Orange, CT with approximately $45 billion in assets and operations in 24 U.S. states, Avangrid has two primary lines of business: networks and renewables. Through its networks business, Avangrid owns and operates eight electric and natural gas utilities, serving more than 3.3 million customers in New York and New England. Through its renewables business, Avangrid owns and operates a portfolio of renewable energy generation facilities across the United States. Avangrid employs approximately 8,000 people and has been recognized by JUST Capital as one of the JUST 100 companies – a ranking of America’s best corporate citizens – in 2024 for the fourth consecutive year. In 2024, Avangrid ranked first among utilities and 12 overall. The company supports the U.N.’s Sustainable Development Goals and was named among the World’s Most Ethical Companies in 2024 for the sixth consecutive year by the Ethisphere Institute. Avangrid is a member of the group of companies controlled by Iberdrola, S.A. For more information, visit www.avangrid.com.

Contacts

Media Contact:
Keaton Thomas
Keaton.thomas@avangrid.com
503-956-9621

AVANGRID, Inc.

NYSE:AGR

Release Versions

Contacts

Media Contact:
Keaton Thomas
Keaton.thomas@avangrid.com
503-956-9621

More News From AVANGRID, Inc.

Avangrid Responds to Severe Storms and Extreme Heat Over Fourth of July Holiday

ORANGE, Conn.--(BUSINESS WIRE)--Avangrid, Inc., a leading energy company and member of the Iberdrola Group, responded to a multi-state severe weather event that impacted more than 283,000 customers across New York, Connecticut and Maine during the Fourth of July holiday weekend. "Over the course of one holiday week, our teams responded to multiple severe weather events across New York, Connecticut and Maine while managing record-breaking temperatures and periods of high energy demand," said Ava...

Avangrid Begins Panel Installation at Oregon Trail Solar, Supports Local Jobs

ARLINGTON, Ore.--(BUSINESS WIRE)--Avangrid, Inc., a leading energy company and member of the Iberdrola Group, today announced that it has begun panel installation at Oregon Trail Solar, a 57 MWdc (41 MWac) energy project located in Gilliam County, Oregon. The milestone marks an important step forward in the project’s construction, which is supporting 200 local union jobs. “Beginning panel installation at Oregon Trail Solar marks meaningful progress in delivering new energy infrastructure in Ore...

Avangrid Designated 2026 Military Friendly Employer During America’s 250th Anniversary

ORANGE, Conn.--(BUSINESS WIRE)--Avangrid, Inc., a leading energy company and member of the Iberdrola Group, announced it earned a 2026 Military Friendly Employer designation from Military Friendly. Military Friendly is the standard that measures an organization’s commitment, effort, and success in creating sustainable and meaningful benefits for the military community. As communities across the country commemorate America’s 250th anniversary, Avangrid is proud to recognize the contributions of...
Back to Newsroom