Rio Tinto to triple Weipa solar capacity and add battery storage to help power operations

MELBOURNE, Australia--(BUSINESS WIRE)--Rio Tinto has approved a new solar farm and battery storage at Weipa in Queensland, in a move that will more than triple the local electricity network’s solar generation capacity and help provide cleaner power to Rio Tinto’s operations.

Under the plans, EDL has been contracted to build, own and operate a 4MW solar plant and 4MW/4MWh of battery storage at Weipa. Work on the battery facilities will start this year, with construction of the whole project expected to be complete by late 2022.

The new solar farm and battery storage will complement the existing 1.6MW solar farm at Weipa, which was completed in 2015 and is also owned and operated by EDL. The 4MWh battery system will be built next to the existing Weipa power station and will help provide a stable power network for Rio Tinto’s Weipa Operations bauxite mines and the Weipa township.

Rio Tinto Aluminium Pacific Bauxite Operations General Manager Michelle Elvy said “The new solar farm and battery storage at Weipa will help us lower our carbon footprint and diesel use in a reliable way.

“The original Weipa solar farm was the largest solar facility at an off-grid Australian mine site at the time it was built, and it played an important role in showing the viability of renewable energy systems in remote locations.

“The new solar farm and battery storage system is part of Rio Tinto’s group-wide commitment to reduce emissions across our operations. There is clearly more work to be done, but projects like this are an important part of meeting our climate targets.”

EDL Chief Executive Officer James Harman said “We welcome the opportunity to continue supporting Rio Tinto to reduce carbon emissions.

“EDL will be leveraging expertise from our hybrid renewable energy systems around Australia to deliver clean and reliable energy for Rio Tinto’s operations and the local community.”

When complete, the combined 4MW solar capacity and 4MW/4MWh battery will provide about 11 gigawatt hours of energy annually. Combined with upgrades to the existing Weipa power generation network, the improvements will reduce Weipa Operations’ diesel consumption by an estimated 7 million litres per year and lower its annual carbon dioxide emissions by about 20,000 tonnes - the equivalent of taking more than 3,750 cars off the road.

Rio Tinto Weipa Operations will purchase electricity from EDL and the new solar plant will be connected directly to the Weipa electricity network.

More information on Rio Tinto’s climate targets can be found here.

riotinto.com

Contacts

Please direct all enquiries to media.enquiries@riotinto.com

Media Relations, UK
Illtud Harri
M +44 7920 503 600

David Outhwaite
M +44 7787 597 493

Media Relations, Americas
Matthew Klar
T +1 514 608 4429

Investor Relations, UK
Menno Sanderse
M: +44 7825 195 178

David Ovington
M +44 7920 010 978

Clare Peever
M +44 7788 967 877

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom

T +44 20 7781 2000
Registered in England
No. 719885

Media Relations, Australia
Jonathan Rose
M +61 447 028 913

Matt Chambers
M +61 433 525 739

Jesse Riseborough
M +61 436 653 412

Investor Relations, Australia
Natalie Worley
M +61 409 210 462

Amar Jambaa
M +61 472 865 948

Rio Tinto Limited
Level 7, 360 Collins Street
Melbourne 3000
Australia

T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

Category: Weipa

Rio Tinto

ASX:RIO

Release Versions

Contacts

Please direct all enquiries to media.enquiries@riotinto.com

Media Relations, UK
Illtud Harri
M +44 7920 503 600

David Outhwaite
M +44 7787 597 493

Media Relations, Americas
Matthew Klar
T +1 514 608 4429

Investor Relations, UK
Menno Sanderse
M: +44 7825 195 178

David Ovington
M +44 7920 010 978

Clare Peever
M +44 7788 967 877

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom

T +44 20 7781 2000
Registered in England
No. 719885

Media Relations, Australia
Jonathan Rose
M +61 447 028 913

Matt Chambers
M +61 433 525 739

Jesse Riseborough
M +61 436 653 412

Investor Relations, Australia
Natalie Worley
M +61 409 210 462

Amar Jambaa
M +61 472 865 948

Rio Tinto Limited
Level 7, 360 Collins Street
Melbourne 3000
Australia

T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

Category: Weipa

More News From Rio Tinto

Rhodes Ridge Joint Venture partners begin $191 million feasibility study on up to 50Mtpa Pilbara iron ore mine

PERTH, Australia--(BUSINESS WIRE)--The Rhodes Ridge Joint Venture has approved a $191 million (A$294 million) (Rio Tinto share $96 million, A$147 million) feasibility study to progress development of the first phase of the Rhodes Ridge project, one of the world’s best undeveloped iron ore deposits, in Western Australia’s Pilbara. The feasibility study will assess development of an operation with initial annual production capacity of 40 to 50 million tonnes of iron ore. The joint venture partner...

Yinhawangka Aboriginal Corporation and Rio Tinto sign Interim Modernised Agreement

PERTH, Australia--(BUSINESS WIRE)--Yinhawangka Aboriginal Corporation and Rio Tinto have signed an Interim Modernised Agreement, marking an important step in their long-standing relationship. This interim agreement builds on the 2013 Participation Agreement between the Yinhawangka People and Rio Tinto. It sets out how both parties will work together and establishes a pathway to a fuller modernised agreement that will govern how Rio Tinto operates on Yinhawangka Country for the long term. The ag...

Rio Tinto’s first Pilbara-made rail car built by Gemco in Karratha

KARRATHA, Australia--(BUSINESS WIRE)--Rio Tinto’s first Pilbara-made iron ore rail car has rolled off the production line in Karratha, as part of a A$150 million partnership with Australian rail industry supplier Gemco Rail to build 100 rail cars in Western Australia and to support local manufacturing. The first Karratha-made rail car follows the completion of 40 Western Australian-made iron ore rail cars under the partnership at Gemco Rail’s Perth facility earlier this year, with the remaining...
Back to Newsroom