SCE Completes Transmission Project to Support California’s Clean Energy Goals

West of Devers transmission line enhances reliability while expanding access to renewable energy, storage

ROSEMEAD, Calif.--(BUSINESS WIRE)--Southern California Edison’s support of California’s clean energy goals hit a tangible milestone in May with the completion of upgrades to SCE’s West of Devers transmission lines. The project increases transmission capacity necessary to bring renewable generation — more than 7,000 megawatts of renewable and battery energy storage resources in the coming years — from desert areas in the eastern part of California to the population centers of the Inland Empire and San Gabriel Valley.

“Completing the West of Devers Project is another giant step in our ability to deliver clean energy throughout our service area,” said Kevin Payne, SCE president and CEO. “While distributed energy resources like rooftop solar and battery energy storage will contribute to decarbonizing our electric infrastructure, large-scale generation and reliable delivery of renewable energy will be vital to achieve California’s ambitious climate goals.”

The project consisted of removing and replacing conductors and supporting structures of four separate circuits of 220-kiloVolt transmission lines through the existing 48-mile corridor from the Devers substation near Palm Springs to the Vista and San Bernardino substations in Grand Terrace and San Bernardino, respectively — about 200 miles of power lines. It triples the capacity of power delivery from 1,600 MW to 4,800 MW, which helps with system reliability into the Southern California population centers during peak summer demand. It took many years of planning, siting, public engagement, licensing and construction to bring this project to fruition.

As part of the West of Devers Project, SCE entered into a transaction with Morongo Transmission for it to invest in the project, which allowed SCE to build the project across the Morongo Indian Reservation. The total cost of the project was $740 million, with Morongo Transmission expected to invest $400 million later this year (upon regulatory approval).

SCE applied in 2013 to the Federal Energy Regulatory Commission and the California Public Utilities Commission requesting approvals to build the project. In 2017, the company received all necessary environmental permits and regulatory approvals to start construction, which began in early 2018. West of Devers went into service about five months before its originally projected timeframe.

“The ability to achieve commercial operation ahead of schedule is a testament to the commitment and dedication of all the project team members and the multitude of stakeholders who contributed to the project’s success,” said Chuck Adamson, principal manager of Major Construction for SCE. “With the complexities that accompany a modern-day transmission project, this achievement cannot be overstated.”

SCE built the project in an environmentally beneficial way by rebuilding within a corridor containing existing transmission lines, despite the unique operational challenges of this approach. The project spans several Riverside and San Bernardino communities, including Banning, Beaumont, Calimesa, Colton, Grand Terrace, Loma Linda, Redlands and other unincorporated areas of Riverside and San Bernardino counties. The corridor also passes through the reservation trust land of the Morongo Band of Mission Indians, a key partner with SCE in its bid to obtain environmental permits.

About Southern California Edison

An Edison International (NYSE: EIX) company, Southern California Edison is one of the nation’s largest electric utilities, serving a population of approximately 15 million via 5 million customer accounts in a 50,000-square-mile service area within Central, Coastal and Southern California.

Contacts

Media Contact: David Song, (626) 302-2255
Investor Relations Contact: Sam Ramraj, (626) 302-2540

Southern California Edison

NYSE:EIX

Release Summary
West of Devers transmission line enhances reliability while expanding access to renewable energy, storage.
Release Versions

Contacts

Media Contact: David Song, (626) 302-2255
Investor Relations Contact: Sam Ramraj, (626) 302-2540

More News From Southern California Edison

Nine Months In, Interest Continues in SCE's Wildfire Recovery Compensation Program

ROSEMEAD, Calif.--(BUSINESS WIRE)--Nine months after launching its Wildfire Recovery Compensation Program, Southern California Edison today announced that community members directly impacted by the Eaton Fire continue to seek compensation and receive payments through the voluntary program. More than 4,000 claims have been submitted through the program. More than 2,400 claimants have been paid, with many more in the pipeline once they finalize their settlements.“Every claim reflects a unique set...

More Than 12,000 Seek Compensation Directly Through SCE for Eaton Fire Recovery

ROSEMEAD, Calif.--(BUSINESS WIRE)--Southern California Edison today announced that more than 12,000 participants have sought compensation directly through its Wildfire Recovery Compensation Program. “The strong participation reflects the importance of providing impacted community members with a fair and accessible path to compensation,” said Pedro J. Pizarro, president and CEO of Edison International, SCE’s parent company. “Our focus is on helping people better understand how the process works...

Southern California Edison Exceeds $750 Million in Relief Offered for Eaton Fire Impacts

ROSEMEAD, Calif.--(BUSINESS WIRE)--Southern California Edison today announced that more than $750 million has been offered to community members through its Wildfire Recovery Compensation Program, underscoring continued interest in the voluntary program for eligible community members impacted by the Eaton Fire.“Behind every claim is a person, family or business working to recover and move forward,” said Pedro J. Pizarro, president and CEO of Edison International, SCE’s parent company. “SCE remain...
Back to Newsroom