LONDON--(BUSINESS WIRE)--Rio Tinto and Turquoise Hill Resources (TRQ) have entered into a memorandum of understanding (MOU), which provides a clear pathway to progress the financing for completion of the Oyu Tolgoi Underground Project in Mongolia and address TRQ’s funding position.

The MOU reflects the parties’ agreement that, subject to timing, availability and terms and conditions being acceptable to both parties, they will:

  • pursue re-profiling of principal debt repayments with lenders under the existing project finance arrangements to better align with the revised mine plan, project timing and cash flows;
  • seek to raise up to $500 million in additional lending under the existing project financing arrangements from selected international financial institutions; and
  • while TRQ continues to explore other options for additional debt funding, which Rio Tinto will consider, Rio Tinto has advised TRQ that it does not currently support or expect to consent to any additional debt or other sources of funding. Rio Tinto and TRQ acknowledge that any balance of the funding required for Oyu Tolgoi to achieve completion of the underground mine will need to be met by way of a TRQ equity offering.

Rio Tinto chief executive of Copper & Diamonds, Arnaud Soirat, said “The MOU agreed today with TRQ provides a clear funding pathway for the completion of the Oyu Tolgoi Underground Project. We will continue working with TRQ and the Government of Mongolia to progress the underground project, which has the potential to unlock the most valuable part of the mine for the benefit of all stakeholders.”

Canadian early warning disclosure

Rio Tinto currently beneficially owns 1,021,966,440 common shares of TRQ, representing approximately 50.8% of the issued and outstanding common shares of TRQ. Rio Tinto also has anti-dilution rights that permit it to acquire additional securities of TRQ so as to maintain its proportionate equity interest in TRQ from time to time.

As the subscription price for and the amount of any equity offering is not determinable at this time, the number of TRQ common shares Rio Tinto will beneficially own following closing of any such equity offering cannot be determined at this time.

Except in connection with any such equity offering, Rio Tinto has no present intention of acquiring additional securities of TRQ. Depending upon its evaluation of the business, prospects and financial condition of TRQ, the market for TRQ’s securities, general economic and tax conditions and other factors, Rio Tinto may directly or indirectly acquire or sell some or all of the securities of TRQ.

This announcement is authorised for release to the market by Rio Tinto’s Group Company Secretary.

Contacts

Steve Allen
Group Company Secretary

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom

T +44 20 7781 2000
Registered in England
No. 719885

Tim Paine
Joint Company Secretary

Rio Tinto Limited
Level 7, 360 Collins Street
Melbourne 3000
Australia

T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

Category: Oyu Tolgoi

Rio Tinto

LSE:RIO

Release Summary
Rio Tinto and Turquoise Hill Resources agree funding plan for Oyu Tolgoi
Release Versions

Contacts

Steve Allen
Group Company Secretary

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom

T +44 20 7781 2000
Registered in England
No. 719885

Tim Paine
Joint Company Secretary

Rio Tinto Limited
Level 7, 360 Collins Street
Melbourne 3000
Australia

T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

Category: Oyu Tolgoi

More News From Rio Tinto

Rio Tinto Canada Fund boosts community investment to C$13 million to better meet the needs of Canadians

MONTREAL--(BUSINESS WIRE)--Rio Tinto is increasing its annual community investment commitment in Canada by 30% through the Rio Tinto Canada Fund, bringing total annual funding to C$13 million to support community-led initiatives across the country. As community needs continue to evolve, the increased investment reflects Rio Tinto’s commitment to supporting solutions that create meaningful, long-term benefits. Canada is home to some of Rio Tinto’s most important operations, partnerships and comm...

Rio Tinto commissions $1.5 billion AP60 smelter expansion in Quebec

SAGUENAY, Canada--(BUSINESS WIRE)--Rio Tinto has successfully started commissioning its US$1.5 billion AP60 smelter expansion at Complexe Arvida in Quebec, marking a major milestone for the deployment of its state-of-the-art, low-carbon aluminium smelting technology. The start-up, which began in March, is expected to be completed by the end of 2026 with all 96 new pots operating. This will increase the plant’s production capacity by approximately 160,000 metric tonnes of primary aluminium annua...

Rio Tinto ships 8 billionth tonne of iron ore from the Pilbara

KARRATHA, Australia--(BUSINESS WIRE)--Rio Tinto has celebrated the shipment of 8 billion tonnes1 of iron ore to global markets from the Pilbara region, 60 years after the company’s first shipment set sail from Western Australia for Japan. The milestone shipment departed from Cape Lambert port aboard the Juno Horizon on 19 May 2026, bound for Nippon Steel Corporation, one of Rio Tinto’s longstanding partners. The achievement reflects six decades of continuous operations in the Pilbara, underpinn...
Back to Newsroom