Spanish Mountain Gold Drilling Intersects 133.57 Metres Grading 1.35 g/t Gold With a Higher-Grade Subset of 25.47 Metres of 4.28 g/t Gold

VANCOUVER, British Columbia--(BUSINESS WIRE)--Spanish Mountain Gold Ltd. (the "Company" or "Spanish Mountain Gold") (TSX-V: SPA) (FSE: S3Y) (OTCQB: SPAUF) is pleased to report additional assay results from seven exploration drill holes within the Orca Fault target trend that were completed as part of its 2025 Fall Diamond Drill program (“2025 Fall Drill Program”) for the Spanish Mountain Gold (“SMG”) project, which is located in the Cariboo Gold Corridor, British Columbia, Canada.

The company has completed approximately 9,864 metres (“m”) of drilling to date of the 9,000 to 10,000 m of exploration drilling planned under the 2025 Fall Drill Program, now continuing into 2026. Assays and geochemistry are pending receipt from the laboratory and/or reporting from five additional drill holes completed within the Orca Fault target area.

Highlights:

  • 25-DH-1322 intersected three separate intervals within 133.57 metres grading 1.35 g/t gold including:
    • 32.37 m of 0.87 g/t gold from 75.43 m including 15.31 m of 1.52 g/t gold;
    • 25.47 m of 4.28 g/t gold from 132.40 m including 14.98 m of 6.42 g/t gold; and
    • 29.07 m of 1.41 g/t gold from 187.47 m including 12.63 m of 2.65 g/t gold.
  • 25-DH-1321 intersected two separate intervals in the drill hole:
    • 101.05 m of 0.58 g/t gold from 30.00 m including 36.30 m of 0.81 g/t gold with a high-grade subset of 6.35 m of 2.58 g/t gold; and
    • 23.00 m of 0.67 g/t gold from 265.50 m including 4.50 m of 1.98 g/t gold.
  • 25-DH-1318 intersected two separate intervals in the top 185.00 m of the drill hole:
    • 40.20 m of 0.90 g/t gold from 180.00 m is the second interval that includes 20.72 m of 1.52 g/t gold with a high-grade subset of 5.00 m of 5.65 g/t gold (see January 6, 2026 news release for the upper interval).

Key Findings:

  • Current exploration drilling assay results continues to intersect significant higher-grade mineralization over 530 m in strike length in the Orca Fault target area (Figure 1 and Figure 4) and the continuity can now be traced across multiple parallel, adjacent drill sections over 80 to 150 m.

Main Deposit – Orca Fault area

Seven additional drill holes were collared and successfully completed (see Figure 3) in the Orca Fault target area, 25-DH-1318 (Figure 3 and Table 1), 25-DH-1319 (Figure 1 and Table 2), 25-DH-1320 (Table 3), 25-DH-1321 (Figure 1 and Table 4), 25-DH-1322 (Figure 2 and Table 5), 25-DH-1323 (Figure 1, Figure 2, and Table 6), and 25-DH-1324 (Figure 1 and Table 7). These drill holes continue to confirm and lend confidence to the extent of the Orca Fault target over 530 m strike length, northwest to southeast, and its geological and structural interpretation within the constraining open pit for the MRE (see July 3, 2025 news release).

Drill hole 25-DH-1322 (Figure 1) is yet another example of an exploration drill hole from the 2025 Fall Drill Program having intersected a very wide zone of high-grade gold mineralization. This drill hole intersected 1.35 g/t gold over 133.57 metres to a downhole depth of 209.00 m that included three significant subintervals (see Table 5). It should be noted that 25-DH-1322 has also provided one of the widest overall intercepts of higher-grade gold mineralization for the project, meaning additional follow-up exploration drilling is required to further define the higher-grade gold mineralization in the Orca Fault target area. Drill hole 25-DH-1322 continues to highlight the growing extent of higher-grade gold mineralization in the near surface, open pit environment, as defined in the recent MRE (see July 3, 2025 news release).

The analytical results from the lower portion of drill hole 25-DH-1318 (see Figure 3 and Table 1) reveal significant, deeper, high-grade mineralization in addition to the near surface analytical results published in the January 6, 2026 news release. These deeper analytical results also correlate to the deeper gold mineralization in drill hole 25-DH-1316 (see Figure 3), adding more information about the prospectivity of the mineral potential of the lithological units at depth.

Drill hole 25-DH-1320 ended prematurely in a fault zone; however, the drill casing was left to revisit later in the program to continue assessing the favourability to the southeast of the Orca Fault target strike length.

All results to date continue to reinforce that tighter exploration drill spacing is unlocking additional mineral potential in the Main deposit. These exploration drill holes are presented on drill sections (Figure 1, Figure 2, and Figure 3) that show the alignment of the higher-grade mineralization to the new Orca Fault target. The location of these drill holes is show on a plan map at the end of the news release (Figure 4).

Table 1: Assay Results for 25-DH-1318

Drill hole

From (m)

To (m)

Width (m)

Gold (g/t)

Apparent True Thickness

25-DH-1318

48.38

109.50

61.12(4)

0.50

Note 3)

Including

48.38

89.42

41.04(4)

0.66

Note 3)

Including

48.38

77.00

28.62(4)

0.78

Note 3)

Including

60.00

74.00

14.00(4)

1.08

Note 3)

 

149.74

153.56

3.82

1.17

Note 3)

180.00

220.20

40.20

0.90

Note 3)

Including

180.00

200.72

20.72

1.52

Note 3)

Including

180.00

185.00

5.00

5.65

Note 3)

Table 2: Assay Results for 25-DH-1319

Drill hole

From (m)

To (m)

Width (m)

Gold (g/t)

Apparent True Thickness

25-DH-1319

10.00

11.20

1.20

1.21

Note 3)

 

24.00

139.20

115.20

0.46

Note 3)

Including

24.00

113.50

89.50

0.53

Note 3)

Including

38.00

89.00

51.00

0.70

Note 3)

Including

38.00

50.45

12.45

1.31

Note 3)

Table 3: Assay Results for 25-DH-1320 (drill hole ended prematurely at 57 m downhole in a fault zone)

Drill hole

From (m)

To (m)

Width (m)

Gold (g/t)

Apparent True Thickness

25-DH-1320

30.00

45.00

15.00

0.43

Note 3)

Including

40.00

45.00

5.00

0.83

Note 3)

Table 4: Assay Results for 25-DH-1321

Drill hole

From (m)

To (m)

Width (m)

Gold (g/t)

Apparent True Thickness

25-DH-1321

30.00

131.05

101.05

0.58

Note 3)

Including

38.00

121.50

83.50

0.66

Note 3)

Including

66.00

102.30

36.30

0.81

Note 3)

Including

66.00

72.35

6.35

2.58

Note 3)

Including

119.00

121.50

2.50

2.10

Note 3)

 

195.65

200.50

4.85

0.72

Note 3)

 

220.20

221.35

1.15

5.01

Note 3)

Including

265.50

288.50

23.00

0.67

Note 3)

Including

281.00

285.50

4.50

1.98

Note 3)

Table 5: Assay Results for 25-DH-1322

Drill hole

From (m)

To (m)

Width (m)

Gold (g/t)

Apparent True Thickness

25-DH-1322

75.43

209.00

133.57

1.35

Note 3)

Including

75.43

107.80

32.37

0.87

Note 3)

Including

75.43

98.87

23.44

1.14

Note 3)

Including

81.00

96.31

15.31

1.52

Note 3)

Including

87.84

94.00

6.16

2.74

Note 3)

Including

87.84

91.70

3.86

3.68

Note 3)

Including

132.40

157.87

25.47

4.28

Note 3)

Including

132.40

152.57

20.17

5.35

Note 3)

Including

137.59

152.57

14.98

6.42

Note 3)

Including

179.93

209.00

29.07

1.41

Note 3)

Including

181.47

206.00

24.53

1.63

Note 3)

Including

181.47

194.10

12.63

2.65

Note 3)

Including

181.47

186.50

6.61

3.95

Note 3)

Table 6: Assay Results for 25-DH-1323

Drill hole

From (m)

To (m)

Width (m)

Gold (g/t)

Apparent True Thickness

25-DH-1323

71.00

181.70

110.70

0.37

Note 3)

Including

71.80

79.50

7.70

0.93

Note 3)

Including

149.00

170.30

21.30

0.60

Note 3)

Including

166.80

170.30

3.50

1.70

Note 3)

 

295.00

336.00

41.00

0.55

Note 3)

Including

323.35

333.00

9.65

1.44

Note 3)

Table 7: Assay Results for 25-DH-1324

Drill hole

From (m)

To (m)

Width (m)

Gold (g/t)

Apparent True Thickness

25-DH-1324

16.00

17.15

1.15

13.47

Note 3)

 

50.45

58.30

7.85

0.53

Note 3)

 

69.00

126.00

57.00

0.54

Note 3)

Including

71.18

89.19

18.01

1.10

Note 3)

Including

78.00

89.19

11.19

1.16

Note 3)

Including

122.00

125.08

3.08

1.42

Note 3)

Notes for Table 1 to Table 7:

1) Reported intersections are calculated using a 0.15 g/t Au cut-off grade.

2) The complete assay table is available on the Company’s website

3) True thickness of mineralization is unknown as the project is still at the exploration stage

4) Assay composites previously released January 6, 2026 from partial return of drill hole 25-DH-1318 from laboratory

The integration of assay results from these seven exploration drill holes strengthens the overall continuity for the new Orca Fault target and the association of higher-grade mineralization over a strike length of 530 m, northwest to southeast (see Figure 1). Stronger continuity is also now being developed spanning multiple, parallel, adjacent drill sections ranging in strike length from 80 to 150 m, northeast to southwest, depending on the location along the 530 m strike length (see Figure 3).

Figure 4 illustrates the locations for seven drill hole results outlined in this news release and the drill holes currently in the assay lab, or in process of being drilled. Drill collar location coordinates are summarized for the 2025 Fall Drill Program in Table 8 at the end of this news release.

Drill Core Processing, Data Verification and Quality Assurance – Quality Control Program (QAQC)

Once received from the drill and processed, all drill core samples were sawn in half, labeled, and bagged. The remaining half of the drill core was securely stored on-site. Numbered security tags were applied to sample shipments to ensure chain of custody compliance. The Company inserts quality control (QC) samples at regular intervals, including blanks and reference materials, for all sample shipments to monitor laboratory performance.

Standards and blanks account for a minimum of 20% of the samples in addition to the laboratory’s internal quality assurance programs. The QAQC program was overseen by the Company’s Qualified Person, Julian Manco, P.Geo, Director of Exploration (as described below).

The data verification process involved a multi-step approach to ensure accuracy and integrity. This included a detailed quality control (QC) analysis of the data, which was performed using both internal and external platforms, such as the MxDeposit™ software. These QC checks involved the analysis of certified reference materials (CRMs), blanks, and duplicates to confirm the reliability of the assay results. In addition, a field inspection of the specific drill intervals mentioned in this release has been conducted to directly observe the geological features and verified the nature of the results presented.

Drill core samples were submitted to MSALABS’s analytical facility in Prince George, British Columbia, for sample preparation and PhotonAssayTM analysis. The MSALABS facilities are accredited to the International Standards ISO/IEC 17025 and ISO 9001 standard for gold and multi-element assays, with all analytical methods incorporating quality control materials at defined frequencies and established data acceptance criteria. MSALABS Inc. is independent of the Company.

PhotonAssayTM

The PhotonAssayTM method utilizes gamma ray analysis for gold detection using the Chrysos PhotonAssayTM instrument (PA1408X). This non-destructive, fully automated technique offers high accuracy for analyzing ores and pulps. Sample preparation begins with drying and crushing up to 1 kg of material to achieve at least 70% passing through a 2-millimetre (mm) sieve. The sample is then riffle split to obtain a suitable aliquot for 2 testing cycles (MSALABS Method CPA-Au1).

The PhotonAssayTM instrument bombards 400- to 600-gram samples contained in sealed containers with gamma rays. These containers remain sealed throughout the process, preserving the sample for potential further testing. The analysis is performed robotically, with results that integrate into existing laboratory management systems. Each sample is accompanied by a reference disc traceable to a Certified Reference Material (CRM). Both the sample and reference disc undergo gamma ray exposure, with signals detected and analyzed to ensure accurate and reliable results. The method offers a gold detection range from 0.015 parts per million (ppm - lower limit) to 10,000 ppm (upper limit). Quality control includes the use of reference materials and blanks, with all results reviewed by a competent person before reporting.

Spanish Mountain Gold implemented two QAQC methodologies to validate the accuracy of PhotonAssayTM results, both demonstrating good comparability: 1) comparative analysis of diverse mineralization styles using Total Au screen metallic methods with both FAS-415 (gravimetric finish) and FAS-211 (AAS finish), and 2) comprehensive testing of both sample aliquots and rejects using FAS-211 (AAS finish). QAQC Testing typically can include the following spot checks: 1) Pulverizing tests to evaluate variability in sample preparation, 2) Cross-analysis at external laboratories using screen metallic method, and 3) Four-cycle radiation testing to identify and calibrate potential variability in gold results with variable radiation intensity.

Multi-Elemental Analysis

For the 2025 drilling campaign Spanish Mountain Gold used IMS-230 method to provide multi-element determination using a four-acid digestion followed by ICP-OES and ICP-MS analysis.

Key Process Steps:

Sample Preparation: Samples are dried and ground to a specific criterion (85% passing 75 microns (μm) for rocks and drill core; 180μm for soils and sediments). A homogeneous 10-gram sample is required. Digestion: Samples undergo sequential digestion with nitric, perchloric, hydrofluoric, and hydrochloric acids, followed by dilution with deionized water.

Analysis: The solution is analyzed via ICP-OES and ICP-MS for multi-element quantification.

Quality Control: The process includes reference materials, blanks, and duplicates, with corrections for spectral interferences and thorough review before final reporting.

Qualified Person

Julian Manco, M.Sc., P.Geo., Director of Exploration with Spanish Mountain Gold, is the Qualified Person as defined under National Instrument 43-101 who has reviewed the technical information in this news release and has approved the content for dissemination.

Abbreviations: metres = m, grams per tonne = g/t, gold = Au, mineral resource estimate = MRE, Spanish Mountain Gold = SMG

About Spanish Mountain Gold Ltd.

Spanish Mountain Gold Ltd. is focused on advancing its 100%-owned Spanish Mountain Gold Project (Project) towards its goal to build the next gold mine in the Cariboo Gold Corridor, British Columbia. On August 18, 2025, the Company filed an NI 43-101 Technical Report on SEDAR+ that sets out the Project’s de-risked and optimized Preliminary Economic Assessment (PEA), with an updated Mineral Resource Estimate (MRE). We will continue to advance the Project to position the Company to make a construction decision in 2027. We are striving to be a leader in community and Indigenous relations by leveraging technology and innovation to build the 'greenest' gold mine in Canada. The Relentless Pursuit for Better Gold means seeking new ways to achieve optimal financial outcomes that are safer, minimize environmental impact and create meaningful sustainability for communities. Details on the Company are available on www.sedarplus.ca and on the Company's website: www.spanishmountaingold.com.

On Behalf of the Board,

“Peter Mah”
President, Chief Executive Officer and Director
Spanish Mountain Gold Ltd.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

FORWARD-LOOKING INFORMATION:

Certain of the statements and information in this press release constitute "forward-looking information". Any statements or information that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "expects", "anticipates", "believes", "plans", "estimates", "intends", "targets", "goals", "forecasts", "objectives", "potential" or variations thereof or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be considered forward-looking information. The Company's forward-looking information is based on the assumptions, beliefs, expectations and opinions of management as of the date of this press release and include but are not limited to statements with respect to, the potential for adding more higher-grade gold mineralization within the pit or outside the current pit design; and the receipt of further results from additional drilling under the 2025 Fall Drill Program, and the plan to make a construction decision in 2027. Other than as required by applicable securities laws, the Company does not assume any obligation to update forward-looking information if circumstances or management's assumptions, beliefs, expectations or opinions should change, or changes in any other events affecting such statements or information. For the reasons set forth above, investors should not place undue reliance on forward-looking information.

Table 8: Drill Collar Information for Drill Holes

Hole ID

EAST

NORTH

ELEV

AZIMUTH

DIP

DEPTH

COMMENT

25-DH-1331A

604595

5827901

1103

120

-60

N/A

In Progress (re-collar)

25-DH-1331

604594

5827899

1103

120

-60

55

Ended early due stuck drill rods

25-DH-1330

604332

5827990

1105

120

-60

N/A

In Progress

25-DH-1329

604467

5827962

1090

120

-60

255

Successfully completed per design

25-DH-1328

604278

5828018

1105

120

-58

402

Successfully completed per design

25-DH-1327

604411

5828026

1088

120

-60

327

Successfully completed per design

25-DH-1326

604327

5827963

1108

120

-60

351

Successfully completed per design

25-DH-1325

604385

5827966

1103

120

-60

309

Successfully completed per design

25-DH-1324

604343

5828053

1080

120

-60

276

Successfully completed per design

25-DH-1323

604286

5828046

1097

120

-60

338

Successfully completed per design

25-DH-1322

604279

5827995

1106

120

-60

231

Successfully completed per design

25-DH-1321

604350

5828016

1099

120

-60

348

Successfully completed per design

25-DH-1320

604561

5827809

1126

120

-60

57

Ended early due to major fault zone

25-DH-1319

604404

5827992

1095

120

-70

198

Successfully completed per design

25-DH-1318

604445

5828098

1055

120

-60

243

Successfully completed per design

25-DH-1317

604186

5828166

1076

120

-60

282

Successfully completed per design

25-DH-1316

604514

5828073

1050

120

-60

177

Successfully completed per design

25-DH-1315

604231

5828163

1075

120

-60

282

Successfully completed per design

25-DH-1314

604160

5828218

1056

120

-70

270

Successfully completed per design

25-DH-1313

604566

5827908

1100

120

-60

204

Successfully completed per design

25-DH-1312

604538

5827921

1095

120

-60

205

Successfully completed per design

25-DH-1311

604590

5827935

1084

120

-60

330

Successfully completed per design

25-DH-1310

604592

5827961

1091

120

-60

211

Successfully completed per design

25-DH-1309

604592

5827958

1071

120

-60

237

Successfully completed per design

25-DH-1308

603280

5829250

966

120

-60

150

Successfully completed per design

25-DH-1307

604565

5827974

1068

120

-60

200

Successfully completed per design

25-DH-1306

603451

5829400

927

120

-60

123

Successfully completed per design

25-DH-1305

603657

5829226

919

120

-60

126

Successfully completed per design

25-DH-1304

604536

5827986

1067

120

-60

225

Successfully completed per design

25-DH-1303

603960

5828754

943

100

-55

156

Successfully completed per design

25-DH-1302

604194

5828180

1066

120

-63

282

Successfully completed per design

25-DH-1301

603708

5829029

929

150

-55

188

Successfully completed per design

25-DH-1300

604388

5828063

1085

120

-60

274

Successfully completed per design

25-DH-1299

604369

5828043

1093

120

-60

336

Successfully completed per design

25-DH-1298

604402

5828088

1074

120

-59

334

Successfully completed per design

25-DH-1297

604354

5828069

1084

120

-59

342

Successfully completed per design

25-DH-1296

604484

5828054

1061

120

-50

180

Successfully completed per design

25-DH-1295

604484

5828054

1061

120

-60

33

Ended early due to drill trace spacing

25-DH-1294

604345

5828120

1075

120

-58

351

Successfully completed per design

25-DH-1293

604284

5828149

1076

120

-60

453

Successfully completed per design

25-DH-1292

604223

5828189

1068

120

-62

270

Successfully completed per design

 

Contacts

For more information, contact:
Peter Mah
(604) 601-3651
info@spanishmountaingold.com

Spanish Mountain Gold Ltd.

TSX VENTURE:SPA

Release Versions

Contacts

For more information, contact:
Peter Mah
(604) 601-3651
info@spanishmountaingold.com

More News From Spanish Mountain Gold Ltd.

Spanish Mountain Gold Engages Laura Stein

VANCOUVER, British Columbia--(BUSINESS WIRE)--Spanish Mountain Gold Ltd. (the "Company" or "Spanish Mountain Gold") (TSX-V: SPA) (FSE: S3Y) (OTCQB: SPAUF) is pleased to announce that it has engaged the services of Laura Stein of New York for shareholder and investor communications. Laura has been providing communication services to the mining industry for over 30 years. Laura will communicate directly with existing shareholders, analysts and prospective investors primarily through email, social...

Spanish Mountain Gold Drilling Intersects 102.36 Metres Grading 0.92 g/t Gold With a High-Grade Subset of 17.00 Metres of 2.12 g/t Gold

VANCOUVER, British Columbia--(BUSINESS WIRE)--Spanish Mountain Gold Ltd. (the “Company” or “Spanish Mountain Gold”) (TSX-V: SPA) (FSE: S3Y) (OTCQB: SPAUF) is pleased to provide additional assay results from five (5) exploration drill holes within the Orca Fault target trend that were completed as part of its 2025 Fall Diamond Drill program (“2025 Fall Drill Program”) for the Spanish Mountain Gold (“SMG”) project, which is located in the Cariboo Gold Corridor, British Columbia, Canada. The compa...

Spanish Mountain Gold Drilling Extends the Orca Fault Target Trend to a Strike Length Over 500 Metres Intersecting Numerous High-Grade Results Including 40.00 Metres Grading 0.98 g/t Gold

VANCOUVER, British Columbia--(BUSINESS WIRE)--Spanish Mountain Gold Ltd. (the "Company" or "Spanish Mountain Gold") (TSX-V: SPA) (FSE: S3Y) (OTCQB: SPAUF) is pleased to provide additional assay results from six exploration drill holes within the Orca Fault target trend and five exploration drill holes from the A12 target that were completed as part of its 2025 Fall Diamond Drill program (“2025 Fall Drill Program”) for the Spanish Mountain Gold (“SMG”) project, which is located in the Cariboo Go...
Back to Newsroom