Announcing Granite’s CM/GC Rehabilitation and Construction Project at SFO

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) announced its Construction Manager/General Contractor (CM/GC) project with San Francisco International Airport (SFO) for the Runway 1R-19L Rehabilitation and Taxiway W Construction Project. This project is a key component of SFO's Capital Improvement Program (CIP), a multi-billion-dollar initiative to modernize and improve the airport's infrastructure, including runways, taxiways, and terminals.

Project Timeline:

  • Preconstruction: June 2025 through January 2026
  • Major Construction: March 2026 through November 2026

The project will rehabilitate Runway 1R-19L and construct Taxiway W between Taxiway A and Taxiway L. It includes upgrades to the hot mix asphalt pavement, lighting infrastructure, drainage, signage, Runway Status Lights (RWLS), sectionals, grooving, and striping. The existing Taxiway F1 will be demolished, and a new Taxiway W will be constructed.

“We are committed to building a lasting collaboration with SFO and all stakeholders to deliver this critical infrastructure efficiently and effectively, while minimizing disruptions for both employees and SFO passengers,” said Granite Vice President of Regional Operations Brent Fogg. “We are honored to partner with the exceptional SFO team to enhance the airfield and uphold SFO’s reputation as the Best Airport in North America.”

Granite will supply asphalt from its Santa Clara Asphalt facility, approximately 185,000 tons of P401 and P403 Mix.

The total anticipated construction value is estimated at $115 million and was included in Granite's second-quarter CAP. The project is expected to begin in March 2026 and continue through November 2026.

About Granite

Granite is America’s Infrastructure Company™. Incorporated since 1922, Granite (NYSE:GVA) is one of the largest diversified construction and construction materials companies in the United States as well as a full-suite civil construction provider. Granite’s Code of Conduct and strong Core Values guide the Company and its employees to uphold the highest ethical standards. Granite is an industry leader in safety and an award-winning firm in quality and sustainability. For more information, visit the Granite website, graniteconstruction.com, and connect with Granite on LinkedIn, X, Facebook, and Instagram.

Contacts

Granite Contacts

Media
Erin Kuhlman 831-768-4111
Investors
Wenjun Xu - 831-761-7861

Granite

NYSE:GVA

Release Versions

Contacts

Granite Contacts

Media
Erin Kuhlman 831-768-4111
Investors
Wenjun Xu - 831-761-7861

More News From Granite

Granite Construction Incorporated Prices $600 Million Senior Notes Offering

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite Construction Incorporated (NYSE: GVA) (“Granite”) announced today that it has priced its previously announced offering of $600.0 million aggregate principal amount of 6.375% senior notes due 2034 (the “Notes”) in a private offering that is exempt from the registration requirements of the Securities Act of 1933 (the “Securities Act”). The Notes will be guaranteed by each of Granite’s existing and future domestic subsidiaries that is a borrower or gua...

Granite Construction Incorporated Announces Private Offering of $600 Million of Senior Notes Due 2034

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite Construction Incorporated (NYSE: GVA) (“Granite”) announced today that it plans to offer $600.0 million aggregate principal amount of senior notes due 2034 (the “Notes”) in a private offering that is exempt from the registration requirements of the Securities Act of 1933 (the “Securities Act”). The Notes will be guaranteed on an unsecured basis by each of Granite’s existing and future domestic subsidiaries that is a borrower or a guarantor under Gra...

Granite Awarded Parks Highway MP 315–325 Reconstruction Project in Alaska

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) announced today that it has been awarded the Parks Highway MP 315–325 Reconstruction (Construction MP 322–325) project by the Alaska Department of Transportation and Public Facilities. Located near Nenana, Alaska, the project is the second of two phases of the Parks Highway MP 319–325 CM/GC program that Granite has been delivering since 2022. The contract value is approximately $32 million. Work includes approximately 1.2 million cubic ya...
Back to Newsroom