Granite and JV Partner Advance Southern Nevada Water Infrastructure with Paradise Hills CMAR Project

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA), in partnership with Contri Construction Company, is pleased to announce the formation of Southern Nevada Construction Partners (SNCP), a joint venture. SNCP has been selected to deliver the preconstruction phase of the Paradise Hills Construction Manager at Risk (CMAR) Project for the Southern Nevada Water Authority (SNWA). This infrastructure initiative is a cornerstone of SNWA’s Horizon Lateral Program, which is designed to enhance long-term water delivery, system reliability, and regional redundancy.

The project includes the installation of approximately 22,000 linear feet of 120-inch steel water pipeline, featuring up to three trenchless crossings beneath critical infrastructure: an existing 108-inch waterline, Interstate I-11, and Union Pacific Railroad tracks. The pipeline will also include multiple valved outlets for future connections to Boulder City, the City of Henderson’s Reservoir R-8, and the Horizon Lateral pipeline.

A new 65 million gallons per day (MGD) pumping station will be constructed, with an initial operating capacity of 35 MGD. The facility will include a single-level pump building with mechanical, electrical, and disinfection systems, surge protection infrastructure, flow metering, and advanced instrumentation and control systems. Site improvements will include civil grading, access roads, perimeter security, and desert-compliant landscaping.

As the JV lead, Granite will perform clearing and grubbing operations, structure excavations and backfill, form/place/strip of concrete structures, installation of access roads along the pipeline alignment, demolition and restoration of existing roadways, and the full installation of all pump station structures and equipment. Contri will be responsible for installing the 120-inch pipeline and associated appurtenances.

“This project showcases our joint venture’s local expertise and collaborative strength,” said Don Sawyer, Granite Area Manager. “Through SNCP, we’re delivering a high-value, future-ready water infrastructure solution that supports the long-term needs of Southern Nevada.”

SNWA awarded SNCP the preconstruction contract which will be completed in December 2026.

Construction is anticipated to begin on January 4, 2027, with completion expected January 2030. Granite’s total estimated construction contract value is $240 million.

About Granite

Granite is America’s Infrastructure Company™. Incorporated since 1922, Granite (NYSE:GVA) is one of the largest diversified construction and construction materials companies in the United States as well as a full-suite civil construction provider. Granite’s Code of Conduct and strong Core Values guide the Company and its employees to uphold the highest ethical standards. Granite is an industry leader in safety and an award-winning firm in quality and sustainability. For more information, visit the Granite website, graniteconstruction.com, and connect with Granite on LinkedIn, X, Facebook, and Instagram.

Contacts

Granite Contacts

Media
Erin Kuhlman 831-768-4111
Investors
Wenjun Xu - 831-761-7861

Granite

NYSE:GVA

Release Versions

Contacts

Granite Contacts

Media
Erin Kuhlman 831-768-4111
Investors
Wenjun Xu - 831-761-7861

More News From Granite

Granite Secures U.S. 101 Rehabilitation Project in Monterey County, California

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) announced today that it has been selected for a significant infrastructure project to rehabilitate an eight-mile stretch of U.S. Highway 101 near King City in Monterey County, California. This project, with an estimated cost of approximately $20 million, will receive federal funding and be included in Granite’s first quarter CAP. This initiative will fix roadway issues by restoring pavement, extending service life, updating safety devices...

Granite Announces Timing of Earnings Release and Investor Conference Call

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE: GVA) will release financial results for the quarter and fiscal year ended December 31, 2025, before market opens on Thursday, February 12, 2026. The Company will host an investor conference call at 8:00 a.m. PT, Thursday, February 12, 2026. The Company invites investors to listen to a live audio webcast of the investor conference call on its Investor Relations website, investor.graniteconstruction.com. The investor conference call will also b...

Granite Leads Joint Venture to Deliver 22nd Street Widening and Bridge Replacement Project in Tucson

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA), lead partner in the Granite-Traylor Joint Venture with Traylor Bros., Inc., has been selected by the City of Tucson for the 22nd Street Widening and Bridge Replacement Project in Tucson, Arizona. The $157 million project will be funded by the City of Tucson, the Regional Transportation Authority, and a $25 million RAISE Grant, and will be included in Granite’s 2025 fourth quarter CAP. This project will rebuild 22nd Street from Kino Parkw...
Back to Newsroom