Rio Tinto provides Iron Ore update following Tropical Cyclone Sean

PERTH, Australia--(BUSINESS WIRE)--Tropical Cyclone Sean delivered record rain along parts of the Pilbara coastline of Western Australia, impacting Rio Tinto rail and port operations.

A railcar dumper at the East Intercourse Island (EII) port facility, which shipped 45 million tonnes of total Rio Tinto Iron Ore shipments in 2024, was flooded after the weather event passed the coast, delivering 274mm to Karratha during 20 January 2025.

Assessments are ongoing. Initial indications suggest the dumper at EII could be offline for three to four weeks, as rectifications works are required to repair flood damage.

Recovery works within the broader Iron Ore system are progressing, with the majority of rail and port operations now returned to operations.

The company is working to mitigate impacts and will provide an update at its full year results on 19 February 2025.

First quarter shipments will be affected. Overall shipment guidance for 2025 remains unchanged.

Contacts

Please direct all enquiries to media.enquiries@riotinto.com


Media Relations,
United Kingdom
David Outhwaite
M +44 7787 597 493

Media Relations,
Australia
Matt Chambers
M +61 433 525 739
Michelle Lee
M +61 458 609 322
Rachel Pupazzoni
M +61 438 875 469

Media Relations,
Canada
Simon Letendre
M +1 514 796 4973
Malika Cherry
M +1 418 592 7293
Vanessa Damha
M +1 514 715 2152

Media Relations,
US
Jesse Riseborough
M +1 202 394 9480

Investor Relations,
United Kingdom
Rachel Arellano
M:
+44 7584 609 644
David Ovington
M +44 7920 010 978
Laura Brooks
M +44 7826 942 797
Wei Wei Hu
M +44 7825 907 230

Investor Relations,
Australia
Tom Gallop
M +61 439 353 948
Amar Jambaa
M +61 472 865 948

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom
T +44 20 7781 2000
Registered in England
No. 719885

Rio Tinto Limited
Level 43, 120 Collins Street
Melbourne 3000
Australia
T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

riotinto.com

Category: Pilbara

Rio Tinto

LSE:RIO

Release Versions

Contacts

Please direct all enquiries to media.enquiries@riotinto.com


Media Relations,
United Kingdom
David Outhwaite
M +44 7787 597 493

Media Relations,
Australia
Matt Chambers
M +61 433 525 739
Michelle Lee
M +61 458 609 322
Rachel Pupazzoni
M +61 438 875 469

Media Relations,
Canada
Simon Letendre
M +1 514 796 4973
Malika Cherry
M +1 418 592 7293
Vanessa Damha
M +1 514 715 2152

Media Relations,
US
Jesse Riseborough
M +1 202 394 9480

Investor Relations,
United Kingdom
Rachel Arellano
M:
+44 7584 609 644
David Ovington
M +44 7920 010 978
Laura Brooks
M +44 7826 942 797
Wei Wei Hu
M +44 7825 907 230

Investor Relations,
Australia
Tom Gallop
M +61 439 353 948
Amar Jambaa
M +61 472 865 948

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom
T +44 20 7781 2000
Registered in England
No. 719885

Rio Tinto Limited
Level 43, 120 Collins Street
Melbourne 3000
Australia
T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

riotinto.com

Category: Pilbara

More News From Rio Tinto

Rio Tinto and Amazon Web Services collaborate to bring low-carbon Nuton copper to U.S. data centres

TUCSON, Ariz.--(BUSINESS WIRE)--Rio Tinto today announces a strategic collaboration with Amazon Web Services (AWS) that will see AWS become Nuton® Technology’s first customer following the breakthrough industrial-scale deployment of the innovative bioleaching technology at the Johnson Camp copper mine in the U.S. last month. Under the two-year agreement, AWS will use the first Nuton copper ever produced in components of its U.S. data centres, while also providing cloud-based data and analytics...

Rio Tinto and BHP explore collaboration to mine up to 200 million tonnes of Pilbara iron ore

PERTH, Australia--(BUSINESS WIRE)--Rio Tinto and BHP have agreed to work together to extract up to 200 million tonnes of iron ore at their neighbouring Yandicoogina and Yandi iron ore operations in the Pilbara. Under two non-binding Memoranda of Understanding (MOUs), the companies will explore the potential for: Collaboration on the development of Rio Tinto’s Wunbye deposit; and BHP to supply its Yandi Lower Channel Deposit ore to Rio Tinto for processing at its existing wet plants under agreed...

Statement regarding Glencore plc (“Glencore”)

LONDON--(BUSINESS WIRE)--Rio Tinto plc and Rio Tinto Limited (together, “Rio Tinto”) note the announcement by Glencore and confirm that Rio Tinto and Glencore have been engaging in preliminary discussions about a possible combination of some or all of their businesses, which could include an all-share merger between Rio Tinto and Glencore. The parties’ current expectation is that any merger transaction would be effected through the acquisition of Glencore by Rio Tinto by way of a Court-sanction...
Back to Newsroom