-

Granite’s CM/GC Work Continues in Denali National Park

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) has been awarded Options W.3A, W.3B and W.4 for the Polychrome Area Improvements Construction Manager/General Contractor (CM/GC) project by the Federal Highway Administration (FHWA) in Denali National Park in Alaska. These construction options, with a combined value of $24,586,571, complete long-lead procurements, fabrication of the steel truss bridge, and construction engineering and fabrication of temporary works for a bridge launching system. This combination of awards brings the total value of awarded options and modifications to $95,634,019 since preconstruction began in January 2023. The final package of work remaining to be negotiated, Option Y, includes supply of miscellaneous materials, erection of the bridge, construction of back walls and approaches, and installation of the thermosyphon system. Option Y design is complete, and negotiation for the construction contract is expected to take place in November this year.

These recently awarded options provide for time-sensitive procurement of materials necessary for a fully productive 2024 construction season. Work planned for the 2024 season includes construction of the bridge abutments and temporary launching system, enabling bridge erection the following season in 2025. “Using the CM/GC process and working closely with the FHWA, its design team, and the National Park Service (NPS) during preconstruction allowed Granite to fully analyze risk, generate efficient work plans, develop a detailed schedule, and, importantly, package the work to reduce overall schedule duration and cost. The result of our preconstruction effort is a well-choreographed approach to maximize the work we construct during the next three seasons,” said Group Project Executive, Todd Keller. The Polychrome Area Improvements project is scheduled to be completed by July 2026.

A major milestone achieved in the 2023 construction season was pioneering and construction of a temporary access route across the active landslide. Establishing this route was critical for mobilization of a 200-ton crawler crane for construction of the west abutment in 2024. “We are pleased we were able to construct this temporary route to a reasonably traversable condition as it allowed NPS maintenance crews and landholders access to the 45 miles of park road and private properties beyond the slide for the first time since 2021,” said Vice President of Regional Operations, Derek Betts.

The Polychrome Area Improvements project is at the Pretty Rocks Landslide which intersects Denali Park Road near its midpoint at Mile 45.4. The project scope includes construction of an approximately 475-foot-long single-span steel truss bridge to span the active landslide. Supporting the bridge and improving ground conditions is a combination of earthwork, micro piles, rock anchors, precast concrete abutments, and thermosyphons. Thermosyphons are part of a passive heat exchange system designed to prevent permafrost from thawing and creating instability.

The CM/GC project delivery method involves the contractor during the design and planning phases, offering a lower risk profile for both the contractor and the owner while increasing the overall value to taxpayers. This process is designed to promote collaboration and to solicit value-adding feedback from the contractor.

About Granite

Granite is America’s Infrastructure Company™. Incorporated since 1922, Granite (NYSE:GVA) is one of the largest diversified construction and construction materials companies in the United States as well as a full-suite civil construction provider. Granite’s Code of Conduct and strong Core Values guide the Company and its employees to uphold the highest ethical standards. Granite is an industry leader in safety and an award-winning firm in quality and sustainability. For more information, visit the Granite website, graniteconstruction.com, and connect with Granite on LinkedIn, X, Facebook, and Instagram.

Contacts

Granite Contacts
Media
Erin Kuhlman - 831-768-4111
Investors
Wenjun Xu - 831-761-7861

Granite

NYSE:GVA

Release Versions

Contacts

Granite Contacts
Media
Erin Kuhlman - 831-768-4111
Investors
Wenjun Xu - 831-761-7861

More News From Granite

Granite Awarded Parks Highway MP 315–325 Reconstruction Project in Alaska

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) announced today that it has been awarded the Parks Highway MP 315–325 Reconstruction (Construction MP 322–325) project by the Alaska Department of Transportation and Public Facilities. Located near Nenana, Alaska, the project is the second of two phases of the Parks Highway MP 319–325 CM/GC program that Granite has been delivering since 2022. The contract value is approximately $32 million. Work includes approximately 1.2 million cubic ya...

Granite to Complete $15M Pavement Preservation Near Chickaloon, Alaska

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE:GVA) announced today that it has been awarded the Glenn Highway MP 66.5 to 92 Pavement Preservation project by the Alaska Department of Transportation and Public Facilities. The approximately $15M contract is federally funded and was included in Granite’s first quarter 2026 CAP. Glenn Highway travels 179 miles from Anchorage to Glennallen. A National Scenic Byway, the road provides access to stunning landscapes and a wealth of outdoor activiti...

Granite Reports First Quarter 2026 Results

WATSONVILLE, Calif.--(BUSINESS WIRE)--Granite (NYSE: GVA) today announced results for the quarter ended March 31, 2026. First Quarter 2026 Results Net loss attributable to Granite totaled $42 million, or $(0.96) per diluted share, compared to net loss attributable to Granite of $34 million, or $(0.77) per diluted share, for the same period in the prior year. Adjusted net income attributable to Granite (1) totaled $12 million, or $0.26 per diluted share, compared to adjusted net income attributa...
Back to Newsroom