Rio Tinto to build first solar plant in Western Australia to power iron ore mine

MELBOURNE, Australia--(BUSINESS WIRE)--Rio Tinto has approved a $98 million (100 per cent basis) investment in a new solar plant at the Koodaideri mine in the Pilbara, Australia, as well as a lithium-ion battery energy storage system to help power its entire Pilbara power network.

The 34 megawatt solar photovoltaic plant is expected to supply all of Koodaideri’s electricity demand during peak solar power generation times and approximately 65 per cent of the mine’s average electricity demand.

The plant, Rio Tinto’s first company-owned solar facility, will consist of an estimated 100,000 panels, covering an area of 105 hectares. Construction is expected to begin later this year, subject to government approvals, and is due to be completed in 2021.

Complementing it will be a new 12MWh battery energy storage system in Tom Price that will provide spinning reserve generating capacity to support a stable and reliable network.

The solar plant and battery are estimated to lower annual carbon dioxide emissions by about 90,000 tonnes compared to conventional gas powered generation. This is the equivalent of taking about 28,000 cars off the road.

Rio Tinto Iron Ore chief executive Chris Salisbury said “The construction of our first solar plant in the Pilbara is a significant milestone for the business and an important step in reducing our carbon footprint in the region.

“We are investigating additional renewable energy options in the Pilbara, as well as other opportunities to reduce emissions across our entire global portfolio, building on the 43 per cent reduction in absolute greenhouse gas emissions since 2008.”

Rio Tinto is working to define new emissions reduction targets from 2020 as part of our transition to a lower carbon world.

Notes for editors

Koodaideri, 100 per cent owned by Rio Tinto, is located approximately 35 kilometres north-west of Rio Tinto's Yandicoogina mine site, and about 110 kilometres from the town of Newman.

Funding for the solar plant and battery sits within Rio Tinto’s existing guidance for sustaining capital expenditure for its iron ore business.

The $2.6 billion Koodaideri mine was approved in November last year with construction commencing earlier this year. Production capacity will be 43 million tonnes annually with first production is expected to commence by the end of 2021.

Rio Tinto's Weipa operation in Queensland sources power from an on-site solar facility.

Contacts

media.enquiries@riotinto.com
riotinto.com

Follow @RioTinto on Twitter

Media Relations, Australia
Jonathan Rose
T +61 3 9283 3088
M +61 447 028 913

Matt Chambers
T +61 3 9283 3087
M +61 433 525 739

Jesse Riseborough
T +61 8 6211 6013
M +61 436 653 412

Media Relations, United Kingdom
Illtud Harri
M +44 7920 503 600

David Outhwaite
T +44 20 7781 1623
M +44 7787 597 493

Media Relations, Americas
Matthew Klar
T +1 514 608 4429

Media Relations, Asia
Grant Donald
T +65 6679 9290
M +65 9722 6028

Investor Relations, Australia
Natalie Worley
T +61 3 9283 3063
M +61 409 210 462

Amar Jambaa
T +61 3 9283 3627
M +61 472 865 948

Investor Relations, United Kingdom
Menno Sanderse
T: +44 20 7781 1517
M: +44 7825 195 178

David Ovington
T +44 20 7781 2051
M +44 7920 010 978

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom
T +44 20 7781 2000
Registered in England
No. 719885

Rio Tinto Limited
Level 7, 360 Collins Street
Melbourne 3000
Australia
T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

Category: Pilbara

Rio Tinto

ASX:RIO

Release Versions

Contacts

media.enquiries@riotinto.com
riotinto.com

Follow @RioTinto on Twitter

Media Relations, Australia
Jonathan Rose
T +61 3 9283 3088
M +61 447 028 913

Matt Chambers
T +61 3 9283 3087
M +61 433 525 739

Jesse Riseborough
T +61 8 6211 6013
M +61 436 653 412

Media Relations, United Kingdom
Illtud Harri
M +44 7920 503 600

David Outhwaite
T +44 20 7781 1623
M +44 7787 597 493

Media Relations, Americas
Matthew Klar
T +1 514 608 4429

Media Relations, Asia
Grant Donald
T +65 6679 9290
M +65 9722 6028

Investor Relations, Australia
Natalie Worley
T +61 3 9283 3063
M +61 409 210 462

Amar Jambaa
T +61 3 9283 3627
M +61 472 865 948

Investor Relations, United Kingdom
Menno Sanderse
T: +44 20 7781 1517
M: +44 7825 195 178

David Ovington
T +44 20 7781 2051
M +44 7920 010 978

Rio Tinto plc
6 St James’s Square
London SW1Y 4AD
United Kingdom
T +44 20 7781 2000
Registered in England
No. 719885

Rio Tinto Limited
Level 7, 360 Collins Street
Melbourne 3000
Australia
T +61 3 9283 3333
Registered in Australia
ABN 96 004 458 404

Category: Pilbara

More News From Rio Tinto

Statement regarding Glencore plc (“Glencore”)

LONDON--(BUSINESS WIRE)--Rio Tinto plc and Rio Tinto Limited (together, “Rio Tinto”) note the announcement by Glencore and confirm that Rio Tinto and Glencore have been engaging in preliminary discussions about a possible combination of some or all of their businesses, which could include an all-share merger between Rio Tinto and Glencore. The parties’ current expectation is that any merger transaction would be effected through the acquisition of Glencore by Rio Tinto by way of a Court-sanction...

Rhodes Ridge Joint Venture partners begin $191 million feasibility study on up to 50Mtpa Pilbara iron ore mine

PERTH, Australia--(BUSINESS WIRE)--The Rhodes Ridge Joint Venture has approved a $191 million (A$294 million) (Rio Tinto share $96 million, A$147 million) feasibility study to progress development of the first phase of the Rhodes Ridge project, one of the world’s best undeveloped iron ore deposits, in Western Australia’s Pilbara. The feasibility study will assess development of an operation with initial annual production capacity of 40 to 50 million tonnes of iron ore. The joint venture partner...

Yinhawangka Aboriginal Corporation and Rio Tinto sign Interim Modernised Agreement

PERTH, Australia--(BUSINESS WIRE)--Yinhawangka Aboriginal Corporation and Rio Tinto have signed an Interim Modernised Agreement, marking an important step in their long-standing relationship. This interim agreement builds on the 2013 Participation Agreement between the Yinhawangka People and Rio Tinto. It sets out how both parties will work together and establishes a pathway to a fuller modernised agreement that will govern how Rio Tinto operates on Yinhawangka Country for the long term. The ag...
Back to Newsroom