YELLOWKNIFE, Northwest Territories--(BUSINESS WIRE)--Dominion Diamond Corporation (TSX: DDC, NYSE: DDC) (the “Company” or “Dominion”) reports Ekati Diamond Mine and Diavik Diamond Mine second fiscal quarter 2017 (May through July) sales, Ekati Diamond Mine production results, and an update on the sale of the Company’s Toronto office building. Unless otherwise specified, all financial information is presented in U.S. dollars.
Highlights
-
Sales:
- Second quarter diamond sales were $160.0 million ($209.7 million in Q2 fiscal 2016).
-
Ekati Production:
- During Q2 fiscal 2017, the Ekati Diamond Mine recovered 0.9 million carats from 0.6 million tonnes of ore processed (Q2 fiscal 2016 – 0.9 million carats recovered from 1.0 million tonnes processed).
- During the quarter, tonnage processed was significantly reduced as a result of the fire at the Ekati process plant that occurred on June 23, 2016 and the subsequent processing shutdown.
- Mining operations continued at the higher value Koala underground and Misery Main open pit and have been paused at the lower value Pigeon and Lynx open pits as a cost reduction measure.
-
Building Sale:
- The Company has entered into a binding agreement to sell its downtown Toronto office building for approximately $84.8 million Canadian dollars.
- The transaction is expected to close during the third fiscal quarter and is subject to customary closing conditions.
Sales
Ekati and
Diavik Rough Diamond Sales
The Company recorded total
second quarter sales of $160.0 million ($209.7 million in Q2 fiscal
2016). Sales in the second quarter were lower than the prior year
primarily due to a high proportion of lower value goods from the Misery
Satellites available for sale in the quarter. Three rough diamond sales
were held during the quarter. The Company plans to hold two rough
diamond sales in the third fiscal quarter of 2017.
Q2 FY 2017 Summary
Sales in millions of US dollars |
Three months ended
Jul 31, 2016 |
Six months ended
Jul 31, 2016 |
|||||
Ekati Rough (100% basis) | $ | 83.3 | $ | 188.4 | |||
Diavik Rough (40% basis) | $ | 76.7 | $ | 149.8 | |||
Total Sales(1) | $ | 160.0 | $ | 338.2 | |||
Carats Sold (000s) |
|||||||
Ekati Rough (100% basis) | 668 | 2,213 | |||||
Diavik Rough (40% basis) | 673 | 1,727 | |||||
Total Carats Sold(1) | 1,341 | 3,940 |
(1) Excluded from the Ekati sales recorded are carats produced and sold from the processing of material during a pre-commercial production period. During the second quarter for fiscal 2017, the Company sold an estimated 116,000 carats of such production for estimated proceeds of $8.3 million. For the six months ended July 31, 2016, the Company sold an estimated 149,000 carats of such production for estimated proceeds of $12.8 million.
The Diamond Market
After
buoyant market conditions in the first quarter, rough prices stabilized
in the second quarter supported by confident U.S. retail demand. The
positive conditions in the first half of the year reduced inventories
throughout the pipeline and improved liquidity in the industry. However
despite the improvements in sentiment, the banks that finance the
industry remain cautious. The retail markets outside the U.S. remain
impacted by the strong U.S. dollar, making jewelry comparatively
expensive in domestic currency terms. Despite declines in the top end
luxury sector, retail demand growth in China is focused on the broader
commercial sector of the market supported by a growing middle class.
Also in the Far East, Japanese demand remains robust supported by luxury
tourism from China. Conversely, the retail markets in Europe, Hong Kong
and the Middle East remain somewhat subdued.
Ekati Production
- Throughput was significantly reduced in the second quarter as a result of the fire at the Ekati process plant that occurred on June 23, 2016 and the subsequent processing shutdown, which is expected to last approximately three months in total.
- Mining operations continued during the second quarter with strong performance from both the Koala underground and Misery Main open pit operations. Mining has been paused at the lower value Pigeon and Lynx open pits as a cost reduction measure.
- During the period, the Ekati Diamond Mine recovered 0.9 million carats from 0.6 million tonnes of ore processed (0.9 million carats from 1.0 million tonnes in Q2 fiscal 2016).
- Carat production was negatively impacted by the process plant shutdown, but benefited from the processing of higher grade Misery Main ore, despite some continued dilution of initial ore as a result of sloughing during the mining of preceding benches.
- During the quarter the Company continued to process significant amounts of low value Misery Satellites material.
- Approximately 1.4 million tonnes of material remained in stockpiles at the end of the second quarter. Higher value Misery Main and Koala ore is planned to be prioritized throughout the remainder of fiscal 2017 when processing recommences.
Ekati Diamond Mine Production (100% basis)
For the three months ended Jul 31, 2016 | For the three months ended Jul 31, 2015 | ||||||||||||
Pipe |
Ore Processed (000s tonnes) |
Carats(1) |
Grade(1) (carats/tonne) |
Ore Processed (000s tonnes) |
Carats(1) (000s) |
Grade(1) (carats/tonne) |
|||||||
Misery Main | 135 | 459 | 3.41 | - | - | - | |||||||
Pigeon | 157 | 64 | 0.41 | - | - | - | |||||||
Fox | - | - | - | 17 | 5 | 0.31 | |||||||
Koala | 204 | 116 | 0.57 | 225 | 179 | 0.80 | |||||||
Koala North | - | - | - | 43 | 23 | 0.53 | |||||||
Misery Satellites(2) | 104 | 217 | 2.08 | 309 | 490 | 1.59 | |||||||
Coarse Ore Rejects(“COR”) (3) | - | - | - | 368 | 227 | 0.62 | |||||||
Total(4) | 600 | 856 | 1.43 | 962 | 924 | 0.96 |
For the six months ended Jul 31, 2016 | For the six months ended Jul 31, 2015 | ||||||||||||
Pipe |
Ore Processed (000s tonnes) |
Carats(1) (000s) |
Grade(1) (carats/tonne) |
Ore Processed (000s tonnes) |
Carats(1) (000s) |
Grade(1) (carats/tonne) |
|||||||
Misery Main | 209 | 663 | 3.17 | - | - | - | |||||||
Pigeon | 406 | 173 | 0.43 | - | - | - | |||||||
Fox | - | - | - | 18 | 5 | 0.29 | |||||||
Koala | 518 | 313 | 0.60 | 453 | 401 | 0.89 | |||||||
Koala North | - | - | - | 96 | 53 | 0.55 | |||||||
Misery Satellite(2) | 440 | 783 | 1.78 | 552 | 830 | 1.50 | |||||||
COR(3) | - | - | - | 695 | 439 | 0.63 | |||||||
Total(4) | 1,573 | 1,932 | 1.23 | 1,814 | 1,728 | 0.95 |
(1) As different ore sources are blended during processing, carats and grade per pipe are estimated using the block models for the ore processed from each pipe, adjusted for the overall reconciliation of total carats recovered against the model. The total carats produced include all incremental production arising as a result of the changes made to the Ekati process plant to improve diamond liberation.
(2) The Misery Satellites include the Misery South and Southwest satellite pipes, which are inferred resources, and Misery Northeast material. Approximately 2,500 tonnes of Northeast material was processed during the six months ended July 31, 2016, at an average grade of 0.98 carats per tonne. The Northeast material is not included in the reserves or resources and is therefore incremental production.
(3) This material is not included in the reserves or resources and is therefore incremental production.
(4) Figures may not add up due to rounding.
Diavik Production
The
Diavik Diamond Mine production results for the second calendar quarter
of 2016 were released on July 18, 2016. Diavik reports to the calendar
year ending December 31, and Ekati reports to the fiscal year ending
January 31. The Company does not report Diavik fiscal production results.
Cautionary Statement Regarding Preliminary Results
The
Company cautions that the Company’s second quarter sales results
disclosed in this news release are preliminary and reflect expectations
as of the date of this news release. Actual reported results are subject
to final review and may vary from what is currently expected because of
a number of factors, including, without limitation, additional or
revised information and changes in accounting standards or policies or
in how those standards are applied. In addition, the preliminary results
contained in this news release do not include all of the measures of
financial performance that would be disclosed in the Company’s interim
financial statements. The Company will provide additional financial
information and related discussion and analysis about its second quarter
financial results when it reports those actual results.
Forward-Looking Information
Certain information
included herein, including information about mining activities and
estimated production from the Ekati Diamond Mine, the estimated timeline
for production to recommence at the Ekati processing plant and
expectations regarding the sale of the Company’s office building,
constitutes forward-looking information or statements within the meaning
of applicable securities laws. Forward-looking information is based on
certain factors and assumptions including, among other things, the
current mine plan for the Ekati Diamond Mine; mining, production,
construction and exploration activities at the Company’s mining
properties; the estimated timeframe to complete the necessary repairs at
the Ekati processing plant; currency exchange rates; world and US
economic conditions; future diamond prices; and the level of worldwide
diamond production. Forward-looking information is subject to certain
factors, including risks and uncertainties, which could cause actual
results to differ materially from what the Company currently expects.
These factors include, among other things, the uncertain nature of
mining activities, including risks associated with underground
construction and mining operations, risks associated with joint venture
operations, risks associated with the remote location of and harsh
climate at the Company’s mining properties, risk of delays in completing
the repairs to the Ekati process plant, risks resulting from the
Eurozone financial crisis, risks associated with regulatory
requirements, the risk of fluctuations in diamond prices and changes in
US and world economic conditions, the risk of fluctuations in the
Canadian/US dollar exchange rate and cash flow and liquidity risks.
Actual results may vary from the forward-looking information. Readers
are cautioned not to place undue importance on forward-looking
information, which speaks only as of the date of this disclosure, and
should not rely upon this information as of any other date. While the
Company may elect to, it is under no obligation and does not undertake
to, update or revise any forward-looking information, whether as a
result of new information, further events or otherwise at any particular
time, except as required by law. Additional information concerning
factors that may cause actual results to materially differ from those in
such forward-looking statements is contained in the Company's filings
with Canadian and United States securities regulatory authorities and
can be found at www.sedar.com
and www.sec.gov,
respectively.
About Dominion Diamond Corporation
Dominion
Diamond Corporation is the world’s third largest producer of rough
diamonds by value. Both of its production assets are located in the low
political risk environment of the Northwest Territories in Canada where
the Company also has its head office. The Company is well capitalized
and has a strong balance sheet.
The Company operates the Ekati Diamond Mine and also owns 40% of the Diavik Diamond Mine. Between the two mining operations, diamonds are currently produced from a number of separate kimberlite pipes providing a diversity of diamond supply as well as reduced operational risk. It supplies premium rough diamond assortments to the global market through its sorting and selling operations in Canada, Belgium and India.
For more information, please visit www.ddcorp.ca